A viral X thread by @TeslaLarry maps 154 sites in 36 states, every US project of about $1 billion and up, and counts $2.45 trillion of announced spending. AI data centres and chip fabs are $1.84 trillion of it, or 75%, by our arithmetic from the thread’s own figures.
The map is a personal compilation, posted on 27 November and seen about 345,000 times. Track the AI sites on our AI data centre map.
Business Pill · Capex and Depreciation
An evergreen Business Engineer explainer on capital spending. It explains the general idea only and does not discuss this map.
The key insight: A viral X compilation by @TeslaLarry counts $2.45 trillion of US projects of about $1 billion and up, $1.29 trillion of it firm; AI data centres and chips are 75% of the headline and 70% of the firm money by our arithmetic, and chips are firmer (61%) than data centres (40%).
What the Thread Counts
The thread separates two totals. “Headline” is the largest announced or filed figure, including later phases. “Firm” is money spent, financed, in a filed first phase or under construction.
On that split, $1.29 trillion of the $2.45 trillion is firm, about 53%. “The gap between those two numbers is mostly ceilings,” the author writes.
By category, AI data centres lead at $1.01 trillion, with $401 billion firm. Chips follow at $826 billion, with $503 billion firm. Energy adds about $300 billion: gas, power plants, nuclear and the grid.
He left out about $2 trillion of company-wide pledges, such as Apple’s $600 billion and Nvidia’s $500 billion, because they “name no single site and overlap the projects above”.

Our Number: AI Is Three Quarters, but Less of It Is Firm
AI data centres and chips are 75% of the headline total and 70% of the firm total, by our arithmetic. AI data centres alone are about 41% of the headline.
Chips are the more solid half: about 61% of the chip dollars are firm, against about 40% for AI data centres, by our arithmetic from the thread’s figures.
Five of the biggest entries show the gap. Project Jupiter, Terafab, Starbase, STACK’s Virginia campus and Nscale’s West Virginia site add up to $553 billion of headline money and about $30 billion firm, or 5%.

We Checked the Biggest Items Against Our Record
TSMC Arizona, $265 billion: matches. Our 25 November piece reports TSMC’s US plan now totals $265 billion, up from the first $65 billion.
Meta Hyperion, $50 billion: matches. Our Louisiana pipeline check found Meta expanding Hyperion to 5 gigawatts at more than $50 billion. The thread puts Louisiana at $285 billion; our check of a different list came to $274 billion.
Starbase Louisiana, $100 billion with nothing firm: consistent. SpaceX bills it at $100 billion, and Louisiana regulators have paused its coastal permit until SpaceX sends more information.
Terafab, $119 billion: differs. A SpaceX update we covered called it the “$100B Terafab”. Its Texas tax deals do run in four phases, as the thread says.
Project Jupiter, $12.8 billion firm: differs. The thread uses the first phase, while the Oracle-tied loan for the New Mexico site is $18 billion, per the FT.
Micron’s New York fabs ($150 billion), STACK in Virginia ($100 billion) and Nscale in West Virginia ($69 billion) are not in our record, so we have not checked them.
The Structural Read
As we read it, the map shows how much of America’s building boom is the AI build-out, and how much of that is still a plan.
Three Implications
FOR INVESTORS Headline figures include later phases; the thread’s firm total is about 53% of the headline.
FOR AI BUILDERS AI data centres are the largest category at $1.01 trillion, with about 40% firm by our arithmetic.
FOR READERS The map is one person’s compilation; we checked five of its biggest entries against our own reporting.
What Is Not Established
The totals are one person’s compilation. His sources, he says, are “company releases, state filings, Reuters, CNBC and Capexwire”, but we could not load the full project list from his linked page on 28 November.
Headline figures include phases that may never be built. Several firm figures are first phases or financing, which can change. This is not investment advice.
The Bottom Line
As we read it, the map shows how much of America’s building boom is the AI build-out, and how much of that is still a plan. Texas leads the states at $462 billion, where data centres are rushing for power permits. We track the money on our AI compute commitments tracker.
97,000+ executives read Business Engineer for the AI strategy frameworks cited by ChatGPT, Claude, and Perplexity.
A note on sourcing. The totals, categories and project figures come from a thread and two charts posted on X by @TeslaLarry on 27 November 2026; they are his compilation, not official data, and we could not load the full project list from his linked page. The checks against TSMC, Meta Hyperion, Starbase, Terafab and Project Jupiter use FourWeekMBA’s earlier reporting, linked in the text. The 75%, 70%, 41%, 61%, 40%, 53%, $553 billion and 5% figures are our arithmetic from the thread’s numbers.
Sources: @TeslaLarry, X thread ‘The American Renaissance, mapped’, 27 Nov 2026 (9 posts and two charts) · FourWeekMBA, 25 Nov 2026: Trump to Break Ground at TSMC Arizona; US Plan Now $265B · FourWeekMBA, 16 Nov 2026: HSBC Sold $300M Oracle-Tied Loan in Mid-80s (Project Jupiter, $18B loan per the FT) · FourWeekMBA, 12 Nov 2026: SpaceX Plans $74B in AI Compute (‘$100B Terafab’) · FourWeekMBA, 26 Nov 2026: Louisiana Asks SpaceX to Fix Its $100B Spaceport Permit · FourWeekMBA, 2 Nov 2026: Louisiana’s $274B AI and LNG Pipeline: $113B Is Committed