Texas Data Center Permit Rush: 474GW Asked, 66.4GW Qualify

Data center developers are rushing to get Texas permits approved before Democrat Gina Hinojosa takes over as governor in January, the Financial Times reported on 26 Nov (excerpts shared on X).

The state environmental regulator, TCEQ, resumed issuing data center permits last week on a directive from outgoing Governor Greg Abbott’s office, the FT said. Our AI data centre map tracks where the big sites are going.

Business Pill · Grid Cost Allocation

An evergreen Business Engineer explainer on grid cost allocation: who pays for new power lines. It explains the general idea only and does not discuss Texas or this report.

The key insight: Texas resumed data center permits on Abbott’s directive and developers are rushing approvals before Hinojosa, who pledged a moratorium, takes over, the FT reported; ERCOT has 474 gigawatts of requests but only 66.4 gigawatts qualified as likely base load.

What the FT Reported

TCEQ granted three air pollution permits, the FT said. They cover SpaceX’s $24 billion gas-fired power plant and supercomputing site near Brownsville, CloudBurst’s power plant near San Marcos and an Atlas Energy Solutions site north-east of Abilene.

We covered the SpaceX permit here. The directive said ERCOT, the state grid operator, had finished gathering information on how data centers affect local communities, according to the FT.

Hinojosa has said she would set a moratorium on new development, end tax breaks for the industry and give local communities more say, the FT reported.

Requests to connect to Texas's grid reached about 5.2 times its record peak demand; the load most likely to be
Requests to connect to Texas’s grid reached about 5.2 times its record peak demand; the load most likely to be connected is about 73% of that peak (our arithmetic).

How Much Power Is Being Asked For

In August, ERCOT was considering more than 474 gigawatts of requests to connect to the grid, the FT said. That is about 5.2 times the grid’s record peak demand of 91.1 gigawatts, set on 22 July 2026 per the EIA (our arithmetic).

Only 204 projects, totaling 66.4 gigawatts, qualified as “base load”, the category ERCOT expects to connect as requested, per an ERCOT update in September cited by the FT. That is about 73% of the record peak (our arithmetic).

A further 158 projects worth 127.9 gigawatts qualified as “studied load”, which the FT said can mean different allocations and longer waits. ERCOT’s interconnection study is only expected to start in April 2027, according to a lawyer cited by the FT.

Timeline: June 2025 Senate Bill 6; 21 September 2026 Abbott halts data center permits; 3 November Hinojosa wins; mid-November TCEQ resumes permits; January 2027 Hinojosa takes office; April 2027 ERCOT interconnection study starts.
Developers have a short window between the permit restart and Hinojosa’s arrival in January, while ERCOT’s grid study only starts in April 2027.

How Texas Got Here

Abbott ordered TCEQ to halt all data center permits on 21 September until ERCOT and the state water board finished their reviews, law firm Foley wrote. We covered developers eyeing other states during the pause.

TCEQ got notice from Abbott’s office that ERCOT had finished its community-impact work, The Texas Tribune reported on 17 Nov. Public Citizen said the agency “has begun unilaterally issuing data center permits” without sharing those results.

Texas’s 2025 grid law, Senate Bill 6, already lets ERCOT curtail large loads of 75 megawatts or more in emergencies, Bracewell noted. Texas is also courting chips: see TSMC’s tax filing and Musk’s Terafab deals.

What Investors Say

“It does feel like there is a meaningful speed bump that is put in the road post-midterms,” Tyler Rosenlicht of Cohen & Steers told the FT. “We do believe all the hyperscaler capex is going to occur. It will just be reallocated a bit.”

The Structural Read

As we read it, the permit is the near-term gate, but ERCOT’s queue decides how much of this gets built.

Three Implications

FOR DEVELOPERS The FT says they are racing to secure permits before the January legislative session under Hinojosa.

FOR THE GRID ERCOT qualified 66.4 gigawatts as likely base load out of more than 474 gigawatts requested, per the FT.

FOR INVESTORS Cohen & Steers expects hyperscaler spending to be reallocated, not cut, the FT reported.

What Is Not Established

The FT did not say how many permit applications are still pending. Hinojosa has not published the details of her proposed moratorium.

This Week In The AI Supercycle

A World Without an Order, and an AI Central Bank Without a Successor

This week’s issue: the week AI memory stayed largely sold out while the people holding the shares paid: the weekly’s argument for why the AI Supercycle is not a dot-com replay, read through geopolitics, macro and technology, with the gap between building and financing the widest we’ve recorded.

Read the full issue →

Business Engineer Framework

The AI Supercycle

The Business Engineer map of who builds, finances and captures value in AI.

Read the Map of AI →

The Bottom Line

Texas reopened the permit window, and developers are racing to use it, the FT reported. As we read it, ERCOT’s queue is the tighter limit.

This article is for information only and is not investment advice.

97,000+ executives read Business Engineer for the AI strategy frameworks cited by ChatGPT, Claude, and Perplexity.

A note on sourcing. The permit resumption, the three permits, the ERCOT queue figures and the Rosenlicht quotes come from the Financial Times of 26 Nov 2026, as shown in excerpts shared on X; we could not read the full FT article. The directive and Public Citizen quote come from The Texas Tribune (17 Nov). The record peak is from the EIA. The 5.2 times and 73% figures are our arithmetic.

Sources: Financial Times, 26 Nov 2026, Texas data centre permits (excerpts shared on X by @firesidealpha) · The Texas Tribune via Route Fifty: Texas regulators are resuming environmental permits for data centers (17-18 Nov 2026) · Foley & Lardner: Abbott directs TCEQ to freeze all data center permits (Sept 2026) · EIA Today in Energy: ERCOT record peak 91.1 GW on 22 July 2026 (primary) · Bracewell: Texas Senate Bill 6 large-load rules (July 2025) · FourWeekMBA: SpaceX’s $24B AI site gets Texas air permit · FourWeekMBA: Texas issued a data center permit 64 days before Hinojosa · FourWeekMBA: Developers eye Utah, Iowa as Texas halts data center permits · FourWeekMBA: AI Data Centre Map