Texas Issued a Data Center Permit 64 Days Before Hinojosa

Texas regulators have resumed reviewing data center permits, ending the pause Governor Greg Abbott ordered on 21 September, The Texas Tribune reported on 17 November.

The state issued an air permit for a data center and gas-fired power plant on 16 November, law firm Gibson Dunn wrote. That is 64 days before Governor-elect Gina Hinojosa, who has pledged a moratorium on new approvals, takes office on 19 January (our arithmetic).

Important: not investment advice

This article is for information and education only. It is not investment, financial, legal or tax advice, and it is not a recommendation or an offer to buy or sell any security, ETF, option or other financial product. FourWeekMBA is not a broker-dealer or a registered investment adviser. IPO shares, leveraged and inverse ETFs, and options carry significant risk, including the loss of your entire investment; leveraged and inverse ETFs reset daily and can lose value quickly. Prices, availability, fees and eligibility change and can differ by country and broker, so check the prospectus and your broker’s terms. Figures marked “our arithmetic” are our own calculations from the cited filings and may contain errors. Do your own research and consider speaking to a licensed financial professional before making any investment decision.

Business Pill · Guardrails Explained

An evergreen Business Engineer explainer on guardrails. It teaches the general idea only and does not discuss Texas.

The key insight: Texas issued an air permit for a data center and gas plant on 16 November, 64 days before Governor-elect Gina Hinojosa, who has pledged a moratorium on new approvals, takes office; an expert told ABC13 a governor can only act on future data centers.

What Changed This Week

The Texas Commission on Environmental Quality got notice from Abbott’s office on 13 November that the grid operator had finished gathering information on community impacts, Gibson Dunn wrote.

“The agency has resumed its normal permit review process,” TCEQ spokesperson Laura Lopez said, per the Tribune. Abbott’s office did not immediately respond to the Tribune.

At least one permit has followed. Politico reported that TCEQ issued an air permit to SpaceX for a $24 billion data center planned in Starbase, FOX 7 Austin reported. We have not read the Politico report.

The dates that decide which Texas data center projects get permits before a new governor can act, per The Texa
The dates that decide which Texas data center projects get permits before a new governor can act, per The Texas Tribune and Gibson Dunn.

What Hinojosa Has Said

On 20 November Wall St Engine posted that Hinojosa will impose a moratorium on new data center permits until the state passes laws, leaving already-approved projects unaffected. The post cites no source.

The pledge itself is not new. ABC13 reported on 7 November that she promised to pause new data centers to “protect Texans”, and we covered it on 6 November.

University of Houston lecturer Nancy Sims said Hinojosa can really only take action on future data centers, per ABC13. “You can’t really freeze mid-construction,” Sims said. Gibson Dunn says the form and scope of her order are not yet defined.

What Comes Next

The grid operator plans to give its findings to the Public Utility Commission on 10 December, with discussion at the 17 December open meeting, the Tribune reported. It had answers from 93% of 465 projects.

Bar chart: Abbott's data center permit pause ran 53 days; 64 days run from the 16 November permit to Hinojosa's inauguration
The permit pause and the window before the new governor, in days (our arithmetic on dates from The Texas Tribune and Gibson Dunn).

The Legislature convenes on 12 January, a week before the inauguration. Sine die is 31 May, and only the governor can call a special session, Gibson Dunn notes.

The stakes are large. Data centers made up 420,812 MW of large loads asking to join the Texas grid as of June, 4.6 times the record peak, as we reported.

The Structural Read

As we read it, permits issued before 19 January matter most, because an expert told ABC13 a governor can really only act on future data centers.

As we read the calendar, ERCOT’s findings reach the PUC on 10 December, before the Legislature convenes on 12 January.

TCEQ spokesperson Laura Lopez, via The Texas Tribune, 17 Nov 2026

“The agency has resumed its normal permit review process”

Three Implications

FOR DATA CENTER DEVELOPERS Texas permits are being processed again, with a new governor who has pledged a moratorium taking office on 19 January.

FOR POWER AND GRID PLANNERS ERCOT’s audit findings go to the PUC on 10 December, from responses covering 93% of 465 projects.

FOR LAWMAKERS The Legislature convenes on 12 January and sine die is 31 May; only the governor can call a special session.

What Is Not Established

We found no statement from Hinojosa dated this week. We do not know how many permits TCEQ will issue before 19 January, or whether her order would reach projects with permits but no construction.

This Week In The AI Supercycle

AI Lost Its Central Banker, the Lab Oligopoly, and the Future of Open Source

This week’s issue: the Nvidia leadership change, read as the AI build-out losing its central banker: who now finances the GPU landlords, backstops the data centres and sponsors open models, and why two labs are becoming the bank.

Read the full issue →

Business Engineer Framework

The AI Supercycle

The Business Engineer map of where value pools in the AI stack.

Read the Map of AI →

The Bottom Line

Abbott’s pause ran 53 days, from 21 September to the 13 November notice, and the 16 November permit came with 64 days left in his term (our arithmetic). An expert told ABC13 a governor can only act on future data centers, and Gibson Dunn says the scope of Hinojosa’s order is not yet defined.

Important: not investment advice

This article is for information and education only. It is not investment, financial, legal or tax advice, and it is not a recommendation or an offer to buy or sell any security, ETF, option or other financial product. FourWeekMBA is not a broker-dealer or a registered investment adviser. IPO shares, leveraged and inverse ETFs, and options carry significant risk, including the loss of your entire investment; leveraged and inverse ETFs reset daily and can lose value quickly. Prices, availability, fees and eligibility change and can differ by country and broker, so check the prospectus and your broker’s terms. Figures marked “our arithmetic” are our own calculations from the cited filings and may contain errors. Do your own research and consider speaking to a licensed financial professional before making any investment decision.

97,000+ executives read Business Engineer for the AI strategy frameworks cited by ChatGPT, Claude, and Perplexity.

A note on sourcing. The resumption, the TCEQ quote, the 93%-of-465 response rate and the 10 and 17 December dates are from The Texas Tribune. The 13 November notice, the 16 November air permit, the session calendar and the special-session rule are from Gibson Dunn’s 18 November alert. The SpaceX permit is Politico’s report as relayed by FOX 7; we did not read Politico. Hinojosa’s pledge and Sims’s quote are from ABC13. The 420,812 MW figure is from ERCOT’s 29 July Senate presentation, as we reported on 10 November. The 53-day and 64-day counts are our arithmetic.

Sources: The Texas Tribune, “TCEQ resumes data center permits,” 17 Nov 2026 · FOX 7 Austin, “Texas data center permits moving forward again following Abbott pause,” 18 Nov 2026 · Gibson Dunn, “Texas Data Center Critical Dates and Procedures Following the 2026 Elections,” updated 18 Nov 2026 · ABC13 via Yahoo News, “Governor-elect Gina Hinojosa vows to pause future data centers until new regulations are in place,” 7 Nov 2026