A Core Scientific project company has registered a $1.3 billion data center building in Hunt County, Texas, with the Texas Department of Licensing and Regulation, the state’s project record shows. The record lists a construction start of 24 November 2026, 56 days before Governor-elect Gina Hinojosa, who has promised a moratorium on data center approvals, takes office on 19 January 2027, by our arithmetic.
Hunt is one of the sites where AMD leases capacity from Core Scientific: about 110 megawatts, according to the company’s July investor presentation. Set against that figure, the registered cost works out to about $11.8 million per leased megawatt, by our arithmetic; the state record itself lists the tenant as “Not Assigned”.
What the State Record Shows
The record, project number TABS2027005763, is titled “Core Scientific – Hunt” at 4852 CR 3507 in Quinlan. Its scope of work reads: “NEW 341,326.37 SF DATA CENTER CORE AND SHELL BUILDING WITH SITE AND INFRASTRUCTURE IMPROVEMENTS”. The completion date is 4 September 2028, and the status is “Project Registered”.
The owner is Telios Quinlan One, LLC, and the design firm is Gensler. The record says the project is “privately funded, on private land for private use”. At $1.3 billion for 341,326 square feet, the shell and site work come to about $3,809 a square foot, by our arithmetic. DCD first reported the filing on 16 November; a ZeroHedge post on X that night called it the first test of the Texas data center freeze.

Business Pill · Who Pays for the Grid
An evergreen Business Engineer explainer on who pays for grid connections. It teaches the general idea only and does not discuss Core Scientific or Texas.
The key insight: As we read the filings, Core Scientific has put a $1.3 billion building on the calendar 56 days before a governor who has promised a moratorium on data center approvals takes office, at a site where it says it already holds an approved ERCOT interconnection ramp schedule; that sets up a test of what a moratorium would cover, on dates we computed from the state record.
What Core Scientific Has Disclosed
Core Scientific closed the purchase of the Hunt County land on 5 May 2026 for about $232.5 million, together with an electric service agreement “expected to support approximately 430 MW of gross utility power capacity”, its quarterly report for the period to 30 September says. With the registered building, that is about $1.53 billion, by our arithmetic.
On 27 July the company signed leases with AMD for 377 MW of critical IT capacity across its Pecos and Hunt County sites in Texas and Muskogee, Oklahoma, its 8-K says, each for a fifteen-year term. The July presentation lists Hunt at about 110 MW, marked as an AMD direct site, with initial delivery estimated for the first half of 2028. Our earlier piece covered Core Scientific’s third quarter.

The Freeze Question
The 10-Q says Core Scientific has an “approved ERCOT interconnection ramp schedule for our Hunt County development”, and that, having secured these arrangements, its “exposure to potential delays or restrictions affecting new large-load interconnection approvals in Texas is limited with respect to the capacity covered by those agreements”.
Hinojosa’s campaign page calls for “an immediate moratorium on data centers to last until the legislature can meet to put in place real protections”. In an October video, she said: “When I am governor I will issue a moratorium — a ban — on all data center approvals until laws can be passed by the Legislature to protect Texans”, The Texas Tribune reported. The Tribune said her statements went beyond Governor Greg Abbott’s “current freeze on environmental permitting and grid connections” for data centers during an audit period.
For scale, ERCOT told the Texas Senate in July it was tracking about 474 GW of large loads seeking to connect, about 90% of them data centers, as our earlier piece on Hinojosa’s freeze reported. CoreWeave has already written to the governor-elect about its Texas sites.
The Structural Read
As we read the 10-Q, Core Scientific separates capacity it has already secured from new large-load approvals, and tells investors its exposure is limited for the capacity its agreements cover.
As we read Hinojosa’s statements, the promised moratorium is aimed at data center approvals until the Legislature passes new laws; the texts we read do not say how it would treat a project that already holds a grid schedule and a registered start date.
Core Scientific, quarterly report for the period ended 30 September 2026
“our exposure to potential delays or restrictions affecting new large-load interconnection approvals in Texas is limited with respect to the capacity covered by those agreements”
Three Implications
FOR CORE SCIENTIFIC Its July presentation estimates initial delivery for AMD at Hunt County in the first half of 2028, while the state record lists completion of the building on 4 September 2028.
FOR AMD The 8-K says AMD leases capacity at Pecos and Hunt County in Texas and Muskogee in Oklahoma, 377 MW in all, each for a fifteen-year term.
FOR TEXAS POLICY The Texas Tribune reported that Hinojosa takes office on 19 January, and that Abbott’s current freeze covers environmental permitting and grid connections during an audit.
The Business Engineer Lens
This story maps onto the Business Engineer framework The State of AI Data Centers.
The framework says: “The structural bottleneck isn’t computing, it’s electrons.”
As we read the Hunt County filings, the asset Core Scientific points investors to is its approved ERCOT ramp schedule, the right to draw power, more than the building itself; the framework predates the filing and does not discuss it.
What Is Not Established
The state record names no tenant, so linking the building to the AMD lease rests on the site, not on the filing; the $11.8 million per megawatt is our arithmetic on that basis. Hinojosa’s statements we read do not say whether a moratorium would reach projects that already hold approvals or a registered start date.
Core Scientific’s filings we read do not mention the governor-elect. We did not see a statement from Core Scientific, AMD or the Hinojosa transition about this building, and we did not contact them. We could read only the opening of ZeroHedge’s article.
The Bottom Line
Core Scientific has registered a $1.3 billion, 341,326-square-foot data center shell in Hunt County, Texas, with construction listed to start on 24 November, 56 days before Gina Hinojosa takes office, by our arithmetic. The company says it holds an approved ERCOT ramp schedule for the site, where AMD leases about 110 MW, and that its exposure to new interconnection restrictions is limited for capacity under those agreements.
95,000+ executives read Business Engineer for the AI strategy frameworks cited by ChatGPT, Claude, and Perplexity.
A note on sourcing. The building details come from the Texas Department of Licensing and Regulation’s project record TABS2027005763, which we read in full. Core Scientific’s land purchase, power agreement, ERCOT schedule and AMD leases come from its 10-Q for the third quarter of 2026 and its July 8-K and investor presentation filed with the SEC. DCD first reported the filing. Hinojosa’s positions come from her campaign page, her post on X and The Texas Tribune’s 4 November report; Abbott’s current freeze is as the Tribune describes it.
The lead was a ZeroHedge post on X; we could read only the opening of its article. The 56 days, the per-megawatt and per-square-foot costs and the $1.53 billion total are our arithmetic. We did not contact Core Scientific, AMD or the Hinojosa transition for this piece.
Sources: TDLR: TABS2027005763, Core Scientific – Hunt · Core Scientific 10-Q, Q3 2026 (5 Nov 2026) · Core Scientific 8-K, AMD leases (28 Jul 2026) · Core Scientific Q2 2026 investor presentation · DCD: Core Scientific files for 285MW data center outside Dallas (16 Nov 2026) · The Texas Tribune: Hinojosa and the data center pause (4 Nov 2026) · Gina Hinojosa campaign page: data centers