Core Scientific was billing about 485 MW of the roughly 590 MW it has leased to CoreWeave as of 5 November, its third-quarter investor presentation shows, about 82% by our arithmetic. The company filed its Q3 2026 results with the SEC on 5 November.
Colocation revenue rose nearly 60% from the previous quarter to $215.4 million, 92.5% of total revenue of $232.9 million, up from 18.4% a year earlier, by our arithmetic. Capital expenditures reached $985.1 million in the quarter, about 7.4 times adjusted EBITDA of $133.6 million.
Business Pill · Take-or-Pay
An evergreen Business Engineer explainer on take-or-pay contracts. It teaches the general idea only and does not discuss Core Scientific, CoreWeave or AMD.
The key insight: Core Scientific was billing about 485 of the roughly 590 MW it has leased to CoreWeave as of 5 November, per its Q3 2026 presentation; colocation revenue of $215.4 million was 92.5% of third-quarter revenue, and capex reached $985.1 million, by our arithmetic and its 8-K.
What Core Scientific Reported
Core Scientific says it was billing for 485 MW of capacity as of 30 September, representing over $700 million in average annualized colocation GAAP revenue. Adjusted EBITDA more than tripled from the previous quarter to $133.6 million, with margins expanding to 57% from 25%.
Net income was $1.18 billion. The company says that was driven by the change in fair value of warrants, a non-cash item tied to its stock price; operating income was $72.4 million. Self-mining revenue fell to $12.3 million from $57.4 million a year earlier, down about 79% by our arithmetic.
“We are nearing full delivery under our first colocation agreement while construction under our second is underway across five campuses,” chief executive Adam Sullivan said.

What Was Posted on X
Wall St Engine’s post on X summarises Core Scientific’s third-quarter figures: revenue of $232.9 million against an estimate of $195 million, adjusted EBITDA of $133.6 million, colocation revenue of $215.4 million and 485 MW of billing capacity. The $195 million estimate is the post’s own; Core Scientific’s release does not give one.
The CoreWeave Contract
The presentation lists five CoreWeave sites: Denton, Texas (about 260 MW), Dalton, Georgia (about 175 MW), Muskogee, Oklahoma (about 70 MW), Marble, North Carolina (about 65 MW) and Austin, Texas (about 20 MW). Dalton is billing about 75 MW, with completion estimated in early 2027.
Core Scientific describes the agreement as a take-or-pay contract at a fixed cost with an annual escalator, a 12-year term with two five-year options, and “No ability to unilaterally terminate”. It puts revenue potential at over $10 billion over the contracts’ term and average annualized colocation GAAP revenue at about $850 million, about $1.44 million per MW a year by our arithmetic.
The presentation also says revenues from the CoreWeave contract are paid directly into a lockbox tied to the $3.3 billion senior secured notes due 2031.
The Second Agreement and the Balance Sheet
The second set of leases totals about 530 MW for AMD and a credit-backed neocloud, across Pecos and Hunt in Texas, Dalton, Muskogee and Auburn, Alabama. Initial delivery for AMD is expected in early 2027, with the full 530 MW delivered by the end of 2028, the presentation says.
Across both, Core Scientific cites about 1.1 GW of customer contracted power and $24 billion or more in contracted revenue. Texas sites account for about 575 MW of the roughly 1,120 MW leased, about 51% by our arithmetic.
Cash and cash equivalents fell from $1.77 billion at 30 June to $803.9 million at 30 September, a decline of about $966 million by our arithmetic. Long-term debt stood at $4.30 billion, against $1.06 billion at the end of 2025.
Go deeper, 5 Nov, 14:03Z: the 10-Q adds a moratorium risk. Core Scientific’s Form 10-Q for the quarter ended 30 September, filed 5 November, adds a risk factor on its data center operations, citing moratoriums on new data center construction and Texas rules that subject large electricity loads to curtailment or disconnection during grid emergencies. The filing says CoreWeave represented approximately 84% of total revenue for the nine months.
Four of the company’s 11 data centers are in Texas, about 36% by our arithmetic. Read the follow-up: Core Scientific Flags Moratoriums; CoreWeave Is 84% of Sales.
Connecting the Coverage
Our related pieces on neoclouds and data-center capacity:
- Neocloud Stocks Fell 36% in a Month; CoreWeave Bonds Near 79: the sector’s month in markets.
- How Microsoft Rents AI Capacity: 3 Neocloud Deals, $70.9B: how a hyperscaler buys capacity it does not build.
- Hinojosa Wants Data Centers to Pay Costs; Queue Is 2.1x Peak: Texas and the large-load queue.
The Structural Read
As we read the presentation, the CoreWeave build-out is close to complete: about 485 of roughly 590 MW were billing as of 5 November, and Dalton, Georgia is the site still ramping, with completion estimated in early 2027.
As we read the income statement, the company’s revenue mix has moved almost entirely to colocation: 92.5% of revenue in the third quarter against 18.4% a year earlier, by our arithmetic.
As we read the balance sheet, the quarter’s $985.1 million of capex came as cash and cash equivalents fell about $966 million and long-term debt stood at about 4.1 times its end-2025 level, by our arithmetic.
Adam Sullivan, Chief Executive Officer, Core Scientific
“With revenue growing and substantial contracted capacity still to deliver, we have built a strong foundation for our next phase of growth.”
Three Implications
FOR COREWEAVE The presentation says revenues from the CoreWeave contract are paid directly into a lockbox tied to the $3.3 billion senior secured notes due 2031.
FOR THE SECOND BUILD The presentation says initial delivery for AMD is expected in early 2027, with the full 530 MW delivered by the end of 2028.
FOR THE BALANCE SHEET Core Scientific reports capex of $985.1 million in the quarter, while cash and cash equivalents fell to $803.9 million from $1.77 billion three months earlier.
The Business Engineer Lens
This story maps onto the Business Engineer framework The State of AI Data Centers.
The framework says: “The structural bottleneck isn’t computing, it’s electrons.”
As we read it, Core Scientific’s presentation is organised around power: it lists customer capacity in megawatts by site, and its AMD reservation spans secured grid power, utility load studies and behind-the-meter solutions. The framework predates these results and does not discuss Core Scientific.
What Is Not Established
The press release does not name CoreWeave or AMD; those names come from the investor presentation. The release gives no revenue or capex guidance, and it does not mention the US election or any permitting change. Core Scientific’s 10-Q was not on EDGAR when we checked.
The MW figures are approximate, the presentation says, and may not add up because of rounding.
The Bottom Line
Core Scientific was billing about 485 of the roughly 590 MW leased to CoreWeave, and colocation made up 92.5% of third-quarter revenue, by our arithmetic. It spent $985.1 million on capex in the quarter while cash fell by about $966 million, as construction on the second, roughly 530 MW set of leases continues.
95,000+ executives read Business Engineer for the AI strategy frameworks cited by ChatGPT, Claude, and Perplexity.
A note on sourcing. Financial figures and the chief executive’s quote come from Core Scientific’s results release, filed with the SEC as Form 8-K Exhibit 99.1 on 5 November. Site, customer and contract details come from its Q3 2026 earnings presentation. Percentages, ratios and per-MW figures are our arithmetic.
Sources: Core Scientific, Q3 2026 results, Form 8-K Ex. 99.1, 5 November 2026 · Core Scientific, Q3 2026 earnings presentation, 5 November 2026 · FourWeekMBA, Neocloud Stocks Fell 36% in a Month, 4 November 2026