Giga’s $1B AI Site Sits Under the 75MW Bar of a 474GW Queue

Giga Energy’s $1 billion AI data center lease in Hunt County, Texas, covered in our 17 November piece, is for a 60MW site. ERCOT, the Texas grid operator, sets 75 MW as the size at which a load enters its Batch Zero interconnection process, so Giga’s campus sits 15 MW under that bar, by our arithmetic.

Above the bar, ERCOT’s own figures show a queue of about 474.7 GW of large-load requests, 90.2% of it data centers, of which 5.9 GW was observed energized: about 1.2%, by our arithmetic. After the governor’s 3 August audit directive, ERCOT paused energizing new data centers of 75 MW or more, with its audit reports due on 10 December.

Business Pill · Capex and Depreciation

An evergreen Business Engineer explainer on capital expenditure and depreciation. It teaches the general idea only and does not discuss ERCOT or Giga Energy.

Go deeper: building an AI data center in Texas, step by step. Disclosed lease rates, the state air registration and its 53-day pause, and ERCOT’s large-load queue and energization pause, in one place: Texas AI Data Centers Explained: $1.67M Leases, 474GW Queue.

The key insight: On ERCOT’s own figures, about 474.7 GW of large loads were seeking to connect to the Texas grid as of June 2026 and 5.9 GW was observed energized, about 1.2% by our arithmetic; Giga Energy’s 60MW campus sits below the 75 MW size at which ERCOT’s Batch Zero process applies.

What ERCOT’s Queue Shows

In a 29 July update to a Texas Senate panel, ERCOT put large-load interconnection requests, as of June 2026, at a total of 474.7 GW through 2033. By status: 284.3 GW had no studies submitted, 135.5 GW was under ERCOT review, 9.9 GW had met Section 9.4 requirements only, 36.0 GW had met Sections 9.4 and 9.5, 3.2 GW was approved to energize but not operational, and 5.9 GW was observed energized.

ERCOT’s “Key Takeaway” was that it is “tracking approximately 474 GW of Large Loads seeking interconnection, of which ~90% are data centers”. Its breakdown lists data centers at 420,812 MW, 90.2% of the total. Loads with no studies submitted are about 60% of the queue, by our arithmetic.

ERCOT large-load interconnection requests by status as of June 2026 (ERCOT update to the Texas Senate, 29 July
ERCOT large-load interconnection requests by status as of June 2026 (ERCOT update to the Texas Senate, 29 July 2026) and Batch Zero conditional classifications (ERCOT board update, 11 September 2026). Shares and sums are our arithmetic.

Where the Audit Stands

On 3 August, Governor Greg Abbott directed the Public Utility Commission and ERCOT to audit data centers in the interconnection process before more could proceed, as Akin Gump summarised. In an 11 September board update, ERCOT said it had “Paused approvals to energize data centers or virtual currency mining facilities (crypto facilities) that are 75 MW or greater”.

The same update gave ERCOT’s conditional Batch Zero classifications: “204 projects (66.4 GW) met the qualifications to be conditionally included as base load” and “158 projects (127.9 GW) met the qualifications to be conditionally included as studied load”. Together that is 362 projects and 194.3 GW, about 41% of the 474.7 GW queue, by our arithmetic.

ERCOT said it will file a Batch Zero Eligibility Verification Report and a Community Impact Review Report with the Commission by 10 December 2026, 22 days from today by our count. The community review also covers medium loads of 25 to 75 MW, per the same update. ERCOT’s Chad Seely told the Commission that 17 large loads, “mostly data centers”, with total peak demand of about 6.6 GW had cleared ERCOT’s gates except approval to energize, as Utility Dive reported.

Where Giga’s 60MW Fits

ERCOT’s Large Load Integration page says entities “wishing to interconnect a load facility of 75 MW or greater through the Batch Zero process” should consult PGRR145. Giga’s release describes Project Clay as “a 60MW GigaBase AI data center” that taps “underutilized capacity on dedicated power infrastructure in the county”, ready for service in spring 2027.

At 60MW, the site is about 0.013% of the 474.7 GW queue, by our arithmetic, and inside the 25 to 75 MW band that ERCOT’s community review covers. Our first follow-up priced its lease at about $1.67 million per MW a year, and our permit-backlog piece found no Giga air registration in the state’s registry.

The Business Lever

The lever is interconnection timing as a cost of AI capacity. ERCOT’s figures show most requested load has not reached a study, and its pause on energizing data centers of 75 MW or more runs until the December audit filings. Sites smaller than that bar, such as Giga’s 60MW campus, fall outside the Batch Zero process as ERCOT’s page defines it, by our reading. Larger projects in our coverage, such as SpaceX’s Texas site, face the full process.

The Structural Read

As we read ERCOT’s status table, about 60% of the requested load had no studies submitted, by our arithmetic, so the queue total is far larger than what has advanced.

As we read ERCOT’s 11 September update, the pause on energizing data centers of 75 MW or more ties new large AI campuses in Texas to the audit filings due on 10 December.

Chad Seely, ERCOT senior vice president, as reported by Utility Dive

“Our goal is to head toward a December 10 filing”

Three Implications

FOR LARGE AI CAMPUSES ERCOT says it paused approvals to energize data centers of 75 MW or greater; its audit reports are due by 10 December 2026.

FOR BATCH ZERO ERCOT conditionally classified 204 projects (66.4 GW) as base load and 158 projects (127.9 GW) as studied load, 194.3 GW in all by our arithmetic.

FOR GIGA ENERGY Its Hunt County campus is 60MW, about 0.013% of the 474.7 GW queue by our arithmetic, and below ERCOT’s 75 MW Batch Zero bar.

The Business Engineer Lens

This story maps onto the Business Engineer framework The State of AI Data Centers.

The framework says: “Companies that solve the power equation will dominate the AI era; those that don’t will watch their chips sit idle.”

As we read it, ERCOT’s queue shows that power equation in one grid: 474.7 GW requested against 5.9 GW energized. The framework predates these figures and does not discuss ERCOT or Giga Energy.

What Is Not Established

Whether Giga’s site needed ERCOT large-load approval, how it connects to the grid and which utility serves it are not established; the release does not say. Whether its 60MW size was chosen with ERCOT’s 75 MW threshold in mind is not established. ERCOT’s queue figures are as of June 2026 and include loads that may be speculative or duplicative; we found no newer ERCOT total. We did not contact Giga Energy or ERCOT.

This Week In The AI Supercycle

AI Lost Its Central Banker, the Lab Oligopoly, and the Future of Open Source

This week’s issue: the Nvidia leadership change, read as the AI build-out losing its central banker: who now finances the GPU landlords, backstops the data centres and sponsors open models, and why two labs are becoming the bank.

Read the full issue →

Business Engineer Framework

The State of AI Data Centers

A Business Engineer analysis of the power, land and capital behind the AI data center build-out.

Read the Map of AI →

The Bottom Line

On ERCOT’s own figures, Texas holds about 474.7 GW of large-load requests with 5.9 GW energized, and new data centers of 75 MW or more cannot energize until the audit. Giga’s 60MW campus sits below that 75 MW bar.

97,000+ executives read Business Engineer for the AI strategy frameworks cited by ChatGPT, Claude, and Perplexity.

A note on sourcing. Queue figures are ERCOT’s own, from its 29 July 2026 update to the Texas Senate (status as of June 2026) and its 11 September 2026 board update on Batch Zero; the 75 MW threshold is from ERCOT’s Large Load Integration page, read on 18 November. The 3 August directive is as summarised by Akin Gump, and Chad Seely’s remarks as reported by Utility Dive.

Giga’s facts are from its 17 November release. Every share, sum and day count is our arithmetic. We did not contact Giga Energy or ERCOT.

Sources: ERCOT Update to the Texas Senate, 29 Jul 2026 · ERCOT Board Item 14: Batch Zero Update, 11 Sep 2026 · ERCOT Large Load Integration page · Utility Dive, ERCOT audit by December · Akin Gump, Texas pauses data center interconnections · Giga Energy release (Project Clay), 17 Nov 2026