Texas AI Data Centers Explained: $1.67M Leases, 474GW Queue

Building an AI data center in Texas runs through three gates: a lease or build deal, a state air registration if the site makes its own power, and the grid operator ERCOT’s process for large loads. This page sets out each gate with the figures from our recent reporting on Giga Energy’s Hunt County lease, SpaceX’s Boca Chica permit and ERCOT’s queue.

Our numbers: four disclosed AI data center leases range from about $1.22 million to $1.87 million per MW a year, a spread of about 1.53x, by our arithmetic. Air registrations still pending under SpaceX’s rule code have waited a median of 39 days, against 11.5 days for new registrations completed before the pause, by our count. Of about 474.7 GW of large loads in ERCOT’s queue, 5.9 GW was observed energized, about 1.2%, by our arithmetic.

Business Pill · Capex and Depreciation

An evergreen Business Engineer explainer on capital expenditure and depreciation. It teaches the general idea only and does not discuss Texas or ERCOT.

The key insight: In Texas the rent for an AI data center is the known number, about $1.22 million to $1.87 million per MW a year across four disclosed leases by our arithmetic; the open number is time, with pending air registrations at a median of 39 days and about 1.2% of ERCOT’s 474.7 GW large-load queue observed energized, by our arithmetic.

What Does an AI Data Center Lease Cost?

Giga Energy said on 17 November that it signed a $1 billion, 10-year lease with an undisclosed US AI cloud provider for a 60MW data center in Hunt County, about $1.67 million per MW a year by our arithmetic, assuming flat payments, which Giga does not disclose. Our comparison set it against three leases whose landlords disclosed value, term and capacity. Cipher Mining’s 15-year Amazon Web Services lease works out to about $1.22 million per MW a year.

TeraWulf’s Fluidstack agreements come to up to $1.85 million, an upper bound because the release says 200+ MW. Applied Digital’s first two CoreWeave leases come to about $1.87 million, all by our arithmetic. Those three were announced in 2025.

The path for an AI data center in Texas with the figures from our reporting: disclosed lease rates (our arithm
The path for an AI data center in Texas with the figures from our reporting: disclosed lease rates (our arithmetic), TCEQ air-registration waits under rule code 6005 (our count, read 18 November 2026), ERCOT’s large-load queue as of June 2026 and its pause on energizing data centers of 75 MW or more (ERCOT, 11 September 2026). Step 2 applies to sites with on-site generation.

When Does a Texas Data Center Need an Air Permit?

A site that generates its own power needs a state air registration for the plant. SpaceX’s planned data center and gas-fired plant near Brownsville is the clearest example: POLITICO reported that the permit approves 35 natural gas-burning turbines producing 750 megawatts, and allows up to 248 tons a year of nitrogen oxides, two tons under the 250-ton threshold that triggers more robust review, including a public hearing. The Texas Commission on Environmental Quality’s registry lists SpaceX’s registration 185303 as ACTIVE, as our SpaceX permit piece reported.

What Was the 53-Day Data Center Permit Pause?

Governor Greg Abbott directed the agency on 21 September to halt “all permits sought by data centers” until ERCOT completed its review. The Texas Tribune reported that the agency received notice on Friday 13 November from Abbott’s office that ERCOT had finished gathering information on community impacts, 53 days after the directive by our count. TCEQ spokesperson Laura Lopez said in a written statement: “The agency has resumed its normal permit review process and will evaluate applications under all applicable state and federal laws and regulations”, the Tribune reported.

On Monday 16 November the registry showed eight registrations completed under rule code 6005, the code on SpaceX’s Boca Chica registration, three of them SpaceX’s; they had waited between 60 and 101 days. Fifty-two projects under the code were still pending across 37 counties, with a median wait of 39 days and the oldest at 117, against a median of 11.5 days for the 28 new registrations completed before 21 September, by our count of the registry.

The code also covers filers that are not data centers. Governor-elect Gina Hinojosa has vowed to keep data center approvals paused until legislators pass new state laws, the Tribune reported.

What Is ERCOT’s 75 MW Batch Zero Bar?

ERCOT’s Large Load Integration page says entities “wishing to interconnect a load facility of 75 MW or greater through the Batch Zero process” should consult PGRR145. ERCOT’s community impact review also covers medium loads of 25 to 75 MW, per its 11 September board update. Giga’s 60MW campus sits 15 MW under the 75 MW bar, by our arithmetic, as our ERCOT piece set out; whether the site needs ERCOT large-load approval is not established.

How Big Is ERCOT’s Large-Load Queue?

In a 29 July update to a Texas Senate panel, ERCOT put large-load interconnection requests, as of June 2026, at 474.7 GW through 2033, with data centers at 420,812 MW, 90.2% of the total. By status, 284.3 GW had no studies submitted, about 60% of the queue by our arithmetic, and 5.9 GW was observed energized. ERCOT’s 11 September update conditionally classed 204 projects (66.4 GW) as base load and 158 projects (127.9 GW) as studied load, 194.3 GW in all, about 41% of the queue by our arithmetic.

Why Are New Large Data Centers Paused in Texas?

On 3 August Abbott directed the Public Utility Commission and ERCOT to audit data centers in the interconnection process before more could proceed, as Akin Gump summarised. In its 11 September board update ERCOT said it had “Paused approvals to energize data centers or virtual currency mining facilities (crypto facilities) that are 75 MW or greater”. ERCOT said it will file its Batch Zero Eligibility Verification Report and Community Impact Review Report with the Commission by 10 December 2026.

ERCOT’s Chad Seely told the Commission that 17 large loads, “mostly data centers”, with total peak demand of about 6.6 GW had cleared ERCOT’s gates except approval to energize, Utility Dive reported.

Grid Power or On-Site Gas?

The two sites in this chain take different routes. Giga says its project taps “underutilized capacity on dedicated power infrastructure in the county”, and our registry search found no Giga Energy air registration. SpaceX’s site builds its own gas plant, and at the TomorrowX summit on 17 November its CFO Bret Johnsen said, by our transcription, that an external turbine provider told SpaceX it could get the turbine but not the blades and vanes for another 18 to 24 months; he said SpaceX is “already building out investment casting house” to make its own. He did not tie his remarks to the Boca Chica site.

The Business Lever

The lever is time to power. As we read the record, each gate adds months: a lease sets the rent, but a site that makes its own power waits on a state registration, and a large grid-connected site waits on ERCOT’s audit and approval to energize, which ERCOT has paused for data centers of 75 MW or more.

The Structural Read

As we read the record, a site that makes its own power trades the grid queue for a state air registration, which the 53-day pause turned into a wait of its own.

As we read ERCOT’s 11 September update, the pause on energizing data centers of 75 MW or more ties every large new grid-connected campus in Texas to the audit reports due on 10 December.

TCEQ spokesperson Laura Lopez, as reported by The Texas Tribune

“The agency has resumed its normal permit review process and will evaluate applications under all applicable state and federal laws and regulations”

Three Implications

FOR DEVELOPERS Disclosed lease rates run about $1.22 million to $1.87 million per MW a year by our arithmetic; the landlords do not disclose payment schedules.

FOR SITES WITH ON-SITE GENERATION Fifty-two air registrations under SpaceX’s rule code were still pending on 18 November, by our count of the TCEQ registry.

FOR LARGE GRID-CONNECTED SITES ERCOT says approvals to energize data centers of 75 MW or greater are paused; its audit reports are due by 10 December 2026.

The Business Engineer Lens

This story maps onto the Business Engineer framework The State of AI Data Centers.

The framework says: “Companies that solve the power equation will dominate the AI era; those that don’t will watch their chips sit idle.”

As we read it, Texas shows that power equation step by step: the lease is signed long before the site can draw power. The framework predates these figures and does not discuss ERCOT, TCEQ or Giga Energy.

What Is Not Established

Whether Giga’s 60MW site needs ERCOT large-load approval, or was sized with the 75 MW bar in mind, is not established. The registry shows rule codes, not equipment, so what SpaceX’s Starbase and Bastrop registrations cover is not established. ERCOT had not published its audit findings in the sources we read, and the governor-elect’s approach to approvals is known only from her campaign vow, as the Tribune reported. The lease rates assume flat payments, which the landlords do not disclose.

This Week In The AI Supercycle

AI Lost Its Central Banker, the Lab Oligopoly, and the Future of Open Source

This week’s issue: the Nvidia leadership change, read as the AI build-out losing its central banker: who now finances the GPU landlords, backstops the data centres and sponsors open models, and why two labs are becoming the bank.

Read the full issue →

Business Engineer Framework

The State of AI Data Centers

A Business Engineer analysis of the power, land and capital behind the AI data center build-out.

Read the Map of AI →

The Bottom Line

In Texas, the rent is the known number: about $1.22 million to $1.87 million per MW a year across four disclosed AI data center leases, by our arithmetic. The open numbers are time: a median of 39 days and counting for pending air registrations after the 53-day pause, and an ERCOT queue of about 474.7 GW in which about 1.2% was energized, with approvals for large new data centers paused until ERCOT’s 10 December reports.

97,000+ executives read Business Engineer for the AI strategy frameworks cited by ChatGPT, Claude, and Perplexity.

A note on sourcing. Queue figures are ERCOT’s own, from its 29 July 2026 update to the Texas Senate (status as of June 2026) and its 11 September 2026 board update on Batch Zero; the 75 MW threshold is from ERCOT’s Large Load Integration page, read on 18 November. The 3 August directive is as summarised by Akin Gump, and Chad Seely’s remarks as reported by Utility Dive.

Giga’s facts are from its 17 November release. Every share, sum and day count is our arithmetic. We did not contact Giga Energy or ERCOT.

Sources: Giga Energy release (Project Clay), 17 Nov 2026 · ERCOT Update to the Texas Senate, 29 Jul 2026 · ERCOT Board Item 14: Batch Zero Update, 11 Sep 2026 · ERCOT Large Load Integration page · Utility Dive, ERCOT audit by December · Akin Gump, Texas pauses data center interconnections