Anthropic’s three GPU cloud deals, with SpaceXAI, Nscale and Lambda, add up to as much as about $206.4 billion, by our arithmetic, and each comes with termination rights, according to the Form S-1 Anthropic filed with the SEC on 26 October 2026. Its deals with Microsoft, Google and Amazon commit it to at least about $269.4 billion “regardless of actual usage”, and are non-cancelable except for the supplier’s uncured breach or, at Microsoft, undelivered tranches.
The suppliers’ own filings show the other side. Nscale’s Form S-1, filed on 18 September 2026, says it has not yet obtained binding commitments for any of the financing it needs to perform its Anthropic agreements. SpaceX’s June prospectus says either party may end its Anthropic agreements on 90 days’ notice.
Business Pill · TAKE-OR-PAY
A short Business Engineer explainer on take-or-pay contracts. It teaches the general idea only and says nothing about Anthropic, its suppliers or their filings.
The key insight: As we read it, the S-1 splits Anthropic’s compute into two kinds of contract: GPU cloud deals with SpaceXAI, Nscale and Lambda that carry termination rights and, for Nscale and Lambda, fees only on delivery, and big-cloud minimums that it says are owed regardless of actual usage.
Update (26 Oct): Anthropic is moving from renting cloud time to leasing its own data centres. Axios reported that the shift pulls Anthropic deeper into the energy supply chain. The S-1 describes an “ongoing transition from a cloud-only, fixed-time arrangement compute model to a hybrid model” that includes directly leased chips hosted in dedicated facilities “leased and operated on our behalf, to our specification”.
It names one operator: under a colocation and services agreement, Fluidstack provides data centre development and operations services to Anthropic. In March 2026, in connection with order forms under that kind of agreement for a US facility, Anthropic guaranteed a data centre provider’s obligations under a power purchase contract, up to a maximum of $500 million. In April it deposited $2.5 billion into an escrow account for a compute and infrastructure lease.
The filing also flags the local risk: New York has paused state permitting for new large facilities and Texas can curtail large loads in grid emergencies, and “opposition to data center development has also become more organized and coordinated across jurisdictions and our public profile may draw particular attention to projects associated with us.” Caveat: the S-1 does not name the provider behind the $500 million guaranty, and we could read only Axios’s headline.
Update, 27 Oct: what the S-1 says its community power commitments are costing. In the same risk factors, Anthropic says it has made, and may make, “voluntary commitments to offset the impact of our data center energy consumption on local communities and electricity ratepayers”, including covering grid infrastructure upgrade costs, procuring new power generation to match its energy needs and investing in curtailment systems for peak demand.
“These commitments have increased, and we expect will continue to increase, our operating costs,” the filing says, adding that Anthropic believes this is “part of a broader emerging trend in the AI industry” and that such commitments “may become increasingly standard or required”.
The S-1 also says higher average temperatures from climate change can increase the power and water used to cool equipment, and lists among its risks physical attacks, “including those motivated by geopolitical events, opposition to AI, and opposition to data center development”.
What the S-1 Lets Anthropic End
The S-1 lists each compute commitment and its exit terms in its discussion of contractual obligations. On SpaceXAI, a SpaceX subsidiary, it says that after initial non-cancelable periods ending in January and March 2027, “each agreement may be cancelled by either party upon 90 days’ advance written notice”.
For Nscale and Lambda, it says fees accrue “only as capacity is delivered to and accepted by us”. On Nscale it adds: “Otherwise, our commitment under each agreement is non-cancelable except in limited circumstances, including Nscale’s failure to meet specified delivery or service availability requirements or an uncured material breach by the applicable Nscale entity.”
Lambda’s August 2026 agreement, about $34.9 billion of its $41.3 billion, can be ended by “either party” if Lambda does not timely secure the facility lease, the S-1 says. Certain Lambda agreements can also be ended per tranche if Lambda misses delivery milestones.
| Supplier | Commitment in the S-1 | Term | Early termination, per the S-1 |
|---|---|---|---|
| SpaceXAI | Up to $120.5 billion; about $3.1 billion a month at full capacity | Into 2029 | Either party, on 90 days’ notice, after initial periods ending January and March 2027 |
| Nscale | Up to about $44.6 billion; fees only as capacity is delivered and accepted | Into 2033 | Limited circumstances, including Nscale missing delivery or availability requirements, or uncured breach |
| Lambda | About $41.3 billion; fees only as capacity is delivered and accepted | Into 2034 | Either party on the ~$34.9 billion August deal if Lambda does not secure the lease; per tranche on missed milestones |
| Microsoft | At least $44.9 billion, regardless of actual usage | Nov 2026 to May 2033 | Microsoft’s uncured breach or, per tranche, undelivered tranches |
| At least about $114.5 billion, regardless of actual usage; true-up if spend falls short | Apr 2026 to Jul 2033 | Google’s uncured breach | |
| Amazon | At least $110.0 billion, regardless of actual usage; true-up if spend falls short | May 2026 to Apr 2036 | Amazon’s uncured breach |
Source: Anthropic, PBC Form S-1, filed with the SEC on 26 October 2026, Management’s Discussion and Analysis (contractual obligations). The $206.4 billion and $269.4 billion totals are our arithmetic and add “up to”, “approximately” and “at least” amounts.

What the Suppliers’ Filings Say
Nscale’s S-1 says its four Anthropic agreements provide for up to about $44.6 billion of payments for NVIDIA Vera Rubin NVL72 GPUs at its Monarch Compute Campus. It says “As of the date of this prospectus, we have not obtained binding commitments for any of the financings required to fund performance under the Anthropic Services Agreements.”
It sets out Anthropic’s rights: “If we fail to deliver any tranche within a specified period after its expected delivery date, Anthropic is entitled to terminate that tranche without liability.” It adds “Anthropic may also terminate the applicable agreement if monthly uptime falls below specified thresholds for sustained periods.” Nscale also has Microsoft statements of work worth up to about $43.8 billion, and says it expects Microsoft and Anthropic to be significant customers in future periods.
SpaceX’s prospectus of 12 June 2026 says its Anthropic agreements cover compute across COLOSSUS and COLOSSUS II, including approximately 325,000 NVIDIA GPUs, at $1.25 billion a month through May 2029. It says “After the initial three-month period, the agreements may be terminated by either party upon 90 days’ notice.” It calls the deal “monetization of unused compute capacity”. Anthropic’s S-1 describes the arrangements as amended through October 2026.
TeraWulf announced on 6 July 2026 a 20-year lease with Anthropic for approximately 401 MW of critical IT load at its Justified Data campus in Hawesville, Kentucky, expected to generate about $19 billion of contracted lease revenue over the initial term. Its release says the lease “is expected to be supported by an investment-grade credit”. Its quarterly report adds two five-year extension options at Anthropic’s election.
Hut 8’s annual report describes a 15-year lease with Fluidstack for 245 MW at its River Bend campus in Louisiana, part of a partnership with Anthropic and Fluidstack, with a base contract value of about $7.0 billion. It says the lease “is supported by a financial backstop from Google, which covers the lease payments and related pass-through obligations for the initial 15-year base term of the lease”.
CoreWeave’s first-quarter 2026 release says it “Signed multi-year agreement with Anthropic to support the development and deployment of Anthropic’s Claude family of AI models”. It gives no value.
| Supplier | Filing | What it says about Anthropic |
|---|---|---|
| Nscale | Form S-1, 18 Sep 2026 | Up to ~$44.6 billion; no binding financing commitments yet; Anthropic can end late tranches without liability |
| SpaceX | Prospectus, 12 Jun 2026 | About 325,000 NVIDIA GPUs; $1.25 billion a month through May 2029; either party, 90 days’ notice |
| TeraWulf | 8-K, 6 Jul 2026; 10-Q | 20-year lease, ~401 MW, ~$19 billion; two five-year extension options at Anthropic’s election |
| Hut 8 | 10-K, FY2025 | 15-year, 245 MW lease with Fluidstack, ~$7.0 billion base, rent backstopped by Google |
| CoreWeave | Q1 2026 release | Multi-year agreement with Anthropic; no value given |
Sources: the companies’ SEC filings as named. The SpaceX terms predate the amendments described in Anthropic’s S-1.
Where the Long Leases Sit
The S-1 separates flexible compute from fixed infrastructure. It says certain of its dedicated power and data center arrangements have initial terms of 20 years and “include take-or-pay compute payment obligations and uncapped fuel cost pass-throughs that apply for the duration of the term regardless of actual utilization”.
It also says it has relied on “arrangements with financing sources or partners who guarantee the lease obligations to support the development of data center capacity”, and names Fluidstack as an operator under a colocation and services agreement.
Connecting the Coverage
Our SpaceXAI piece listed Anthropic’s compute commitments and the 90-day term. Our neocloud piece reported Nebius and CoreWeave bonds at record lows. Our cloud billing piece showed the big clouds billing about 48% of Anthropic’s revenue. Our S-1 piece covered the headline numbers. What is new here is the supplier side: the filings of Nscale, SpaceX, TeraWulf, Hut 8 and CoreWeave.
The Structural Read
As we read it, the termination rights sit with the newer suppliers: SpaceXAI can be cancelled by either party on 90 days’ notice after early 2027, and Nscale and Lambda tranches can be ended if capacity is late or the lease is not secured, the S-1 says.
Nscale’s own S-1 says it has not yet obtained binding commitments for any of the financing needed for its Anthropic agreements. As we read it, that puts the build-out risk on the supplier side until the financing closes.
As we read it, the long leases at TeraWulf and Hut 8 are a different shape: 20 years and 15 years, with investment-grade credit support expected at TeraWulf and a Google backstop at Hut 8, according to their filings.
Nscale Ltd Form S-1, 18 September 2026
“If we fail to deliver any tranche within a specified period after its expected delivery date, Anthropic is entitled to terminate that tranche without liability.”
Three Implications
FOR GPU CLOUD SUPPLIERS Nscale’s S-1 says its Anthropic agreements include delivery milestones, uptime requirements and termination rights, and that no binding financing is yet in place.
FOR INVESTORS Anthropic’s S-1 puts up to about $206.4 billion of commitments, by our arithmetic, in GPU cloud deals with termination rights, and at least about $269.4 billion in big-cloud minimums owed regardless of actual usage.
FOR DATA CENTER LANDLORDS TeraWulf’s filings describe a 20-year Anthropic lease with extension options at Anthropic’s election; Hut 8’s describes a Fluidstack lease backstopped by Google for its base term.
The Business Engineer Lens
This story maps onto the Business Engineer framework The AI Capex Map & The State of AI Hyperscalers.
The framework puts neoclouds at about $60 billion of 2026 compute capex, within a cycle it totals at about $1.04 trillion.
As we read it, the S-1 shows how that neocloud tier is contracted by one of its largest buyers: with termination rights and delivery conditions that the big-cloud minimums do not carry. The framework was published in May 2026 and does not discuss this filing.
What Is Not Established
The S-1 leaves its total committed spend blank. The TeraWulf release and quarterly report passages we read describe no termination terms, and Hut 8’s annual report names Fluidstack, not Anthropic, as its tenant. We found no SEC filing from Lambda, so its terms here come from Anthropic’s S-1 alone. None of the filings says any party intends to end an agreement.
The Bottom Line
Anthropic’s S-1 gives it termination rights in up to about $206.4 billion of GPU cloud deals with SpaceXAI, Nscale and Lambda, while its at least $269.4 billion of Microsoft, Google and Amazon commitments run regardless of actual usage. Nscale’s own S-1 says its Anthropic deal still awaits binding financing.
95,000+ executives read Business Engineer for the AI strategy frameworks cited by ChatGPT, Claude, and Perplexity.
A note on sourcing. Anthropic’s figures and terms are from its Form S-1 filed with the SEC on 26 October 2026 (Management’s Discussion and Analysis and Risk Factors). Supplier figures are from Nscale’s Form S-1 of 18 September 2026, SpaceX’s prospectus of 12 June 2026, TeraWulf’s 8-K of 6 July 2026 and quarterly report, Hut 8’s annual report for 2025 and CoreWeave’s first-quarter 2026 release. Totals marked as our arithmetic add unlike amounts. This is not investment advice. We did not contact the companies.
Sources: Anthropic, PBC Form S-1, 26 Oct 2026 · Nscale Ltd Form S-1, 18 Sep 2026 · SpaceX prospectus (424B4), 12 Jun 2026 · TeraWulf 8-K, 6 Jul 2026 · Hut 8 Form 10-K, FY2025 · CoreWeave Q1 2026 release