SB Energy Restates 2 Quarters: OpenAI Warrants Off by $827M

SB Energy, the SoftBank-controlled developer building data center campuses for OpenAI, has restated its first two quarters of 2026, its third amended IPO prospectus, filed on 19 November, shows.

The error was in how it valued the warrants it gave OpenAI. At 30 June the warrant liability was understated by $826.6 million, about 15% of the $5.49 billion first reported, by our arithmetic.

It is SB Energy’s first filing since 21 September. The price range is still blank. We track deals like this one on our AI compute commitments tracker.

Business Pill · Concentration Explained

An evergreen Business Engineer explainer on customer concentration. It teaches the general idea only and does not discuss SB Energy.

The key insight: SB Energy’s 19 November prospectus restates its March and June 2026 quarters after it understated the OpenAI warrant liability by up to $826.6 million, about 15%, by our arithmetic; it says the related material weakness has not been remediated.

What the Filing Restates

Management “identified an error in the determination of certain valuation inputs to reflect the participation terms of the instrument,” the prospectus says, for both the March and June quarters.

At 31 March the warrant liability was understated by $753.1 million. At 30 June it was understated by $826.6 million, the filing shows.

In both quarters the value of the deferred lease incentive at lease inception was understated by $957.2 million, with a $197.5 million adjustment to contributed capital.

SB Energy’s restated June balance sheet puts the OpenAI warrant liability $826.6 million, about 15%, abo
SB Energy’s restated June balance sheet puts the OpenAI warrant liability $826.6 million, about 15%, above the figure first reported.

The Warrants Behind It

The warrants were issued to OpenAI under an agreement amended on 17 August 2026. There are 3,991,809 of them, at a nominal exercise price of $0.01 a share, the prospectus says.

Of those, 1,737,867 are vested or vest when the offering prices. The other 2,253,942 stay unvested after the IPO.

Earlier filings described them as a lease incentive for OpenAI signing a data center lease, as we reported in October.

What It Did to the Numbers

Restated, the six-month net loss rises from $3.19 billion to $3.26 billion, a $66.9 million difference. The March quarter’s loss narrows by $6.5 million.

Total liabilities at 30 June rise from $11.41 billion to $12.24 billion, the restated balance sheet shows.

The Third Quarter Swing

For the nine months to 30 September, SB Energy reported revenue of $177.1 million and a net loss of $1.90 billion, about 3.9 times the year before, by our arithmetic.

That nine-month loss is smaller than the restated six-month loss. By our arithmetic, the warrant line turned into a gain of about $1.44 billion in the third quarter.

The valuation inputs moved over the same period. The equity value of Energy Global, LP used to price the warrants fell from $44.5 billion at 30 June to $38.7 billion at 30 September, a 13% drop by our arithmetic. Reading that as the main driver of the gain is our inference; the filing does not spell it out.

Bar chart of the Energy Global equity value SB Energy used to value OpenAI's warrants: 29.8 billion dollars on 9 January 2026, 30.7 billion on 31 March, 44.5 billion on 30 June and 38.7 billion on 30 September.
The equity value behind the warrant model fell 13% between June and September, by our arithmetic, over the same quarter the warrant line swung to a gain.

The Control Weakness

The September prospectus named a material weakness for 2024 and 2025 only. The new one extends it to the March and June 2026 quarters, citing controls over “accounting for complex transactions.”

“As of September 30, 2026, this material weakness has not been remediated,” the filing says. We follow the wider AI spending debate on our AI bubble page.

The Structural Read

As we read it, the restatement matters less for the size of the loss, which moved by $66.9 million, than for what it says about how hard OpenAI’s stake is to value.

As we read it, a warrant line that swings by more than a billion dollars a quarter will dominate SB Energy’s reported profit until those warrants settle.

SB Energy S-1/A No. 3, 19 Nov 2026

“As of September 30, 2026, this material weakness has not been remediated.”

Three Implications

FOR SB ENERGY’S IPO The new prospectus still has no price range, and adds two restated quarters and a wider material weakness, per the filing.

FOR OPENAI It holds 3,991,809 warrants at $0.01 a share, 1,737,867 of them vested or vesting at pricing, per the prospectus.

FOR READERS OF AI INFRASTRUCTURE FILINGS The warrant line moved from a $2.64 billion six-month charge to a $1.20 billion nine-month charge, per the filing; the gap is our arithmetic.

What Is Not Established

The prospectus does not give a price range or an IPO date. It does not say how the error came to light, beyond that management identified it. The third-quarter figures are our arithmetic from the nine-month and restated six-month statements.

This Week In The AI Supercycle

A World Without an Order, and an AI Central Bank Without a Successor

This week’s issue: the week AI memory stayed largely sold out while the people holding the shares paid: why the AI Supercycle is not a dot-com replay, read through geopolitics, macro and technology, with the gap between building and financing the widest we’ve recorded.

Read the full issue →

Business Engineer Framework

The AI Supercycle

The Business Engineer map of who builds, finances and captures value in AI.

Read the Map of AI →

The Bottom Line

SB Energy’s new prospectus restates two quarters because it undervalued OpenAI’s warrants by up to $826.6 million, and says the related control weakness is still open. It puts its backlog at about $439 billion against $177.1 million of nine-month revenue.

97,000+ executives read Business Engineer for the AI strategy frameworks cited by ChatGPT, Claude, and Perplexity.

A note on sourcing. Every SB Energy figure and quote is from its S-1 amendments of 21 September and 19 November 2026 on SEC EDGAR. Percentages, multiples, the third-quarter warrant swing and the implied third-quarter result are our arithmetic. This is not investment advice.

Sources: SB Energy, Inc., Amendment No. 3 to Form S-1, SEC, 19 Nov 2026 · SB Energy, Inc., Amendment No. 2 to Form S-1, SEC, 21 Sep 2026