Oracle has signed $288 billion of data center leases that have not started yet, per its 10-Q. The filing says they are generally expected to start between the second quarter of fiscal 2027 and fiscal 2029, for terms of 15 to 19 years, and are not yet on its balance sheet.
That is about 4.6 times the $63.2 billion of future lease payments already on its books, for operating and finance leases before discounting, per the same filing (our arithmetic). The filing does not tie them to any customer; Oracle said on Friday that its OpenAI contract is fully funded. Live price and key dates are on our Oracle stock page.
Important: not investment advice
This article is for information and education only. It is not investment, financial, legal or tax advice, and it is not a recommendation or an offer to buy or sell any security, ETF, option or other financial product. FourWeekMBA is not a broker-dealer or a registered investment adviser. IPO shares, leveraged and inverse ETFs, and options carry significant risk, including the loss of your entire investment; leveraged and inverse ETFs reset daily and can lose value quickly. Prices, availability, fees and eligibility change and can differ by country and broker, so check the prospectus and your broker’s terms. Figures marked “our arithmetic” are our own calculations from the cited filings and may contain errors. Do your own research and consider speaking to a licensed financial professional before making any investment decision.
Business Pill · Free Cash Flow
An evergreen Business Engineer explainer. It teaches the general idea only and does not discuss this report.
The key insight: Oracle has $288 billion of data center leases signed but not yet started, about 4.6 times the lease payments already on its books, while quarterly capital spending rose to $28.5 billion from $8.5 billion (Oracle 10-Q; our arithmetic).
What Is Being Built
Oracle’s post on X said its Abilene campus, “where Astra-6 was trained, is nearly complete.” It said Shackelford, “our next gigawatt-scale campus, is fully permitted,” and that the handover of Nvidia Vera Rubin racks is on track for the coming weeks.
The money already spent shows in the 10-Q. Capital spending was $28.5 billion in the quarter to 31 August, against $8.5 billion a year earlier. That is about 3.4 times as much (our arithmetic).
Construction in progress, mostly servers, networking gear and leasehold improvements still to be deployed at its data centers, rose to $48.5 billion from $40.0 billion on 31 May. That is about 21% in three months (our arithmetic).


Two Kinds of Commitment
The 10-Q says the leases are substantially all related to data center arrangements. Separately, Oracle lists $34.2 billion of purchase obligations, mainly long-term deals to buy parts for its cloud equipment and to supply power to its data centers, per the 10-Q.
Equipment already on the books reached $77.8 billion, about three times its buildings, as we reported. Depreciation, the yearly cost of that gear wearing out, was $3.2 billion in the quarter against $1.4 billion a year earlier.
What It Is Paid For With
Oracle’s remaining performance obligations, the contracted revenue it has not yet earned, were $664 billion at 31 August. That compares with $455 billion a year earlier, up about 46% (our arithmetic).
Oracle expects about 13% of that $664 billion as revenue in the next 12 months, per the 10-Q. That is about $86 billion (our arithmetic). The OpenAI work sits in our AI compute commitments tracker.
The Structural Read
As we read it, most of Oracle’s AI build is still a promise on paper: leases that start between fiscal 2027 and 2029.
As we read it, the $664 billion backlog is what Oracle points to as the money that pays for those leases.
Oracle, on X, 20 Nov 2026
“Shackelford, our next gigawatt-scale campus, is fully permitted”
Three Implications
FOR THE BALANCE SHEET $288 billion of leases are not recorded yet and are generally expected to start between the second quarter of fiscal 2027 and fiscal 2029 (10-Q).
FOR SPENDING capital spending of $28.5 billion in one quarter, about 3.4 times a year earlier (10-Q; our arithmetic).
FOR REVENUE a $664 billion backlog, with about 13% expected within 12 months (10-Q).
What Is Not Established
The 10-Q does not split the $288 billion by site or by customer, and it does not name OpenAI. Oracle did not say how much of the lease bill each campus carries. Our 4.6 times ratio assumes the $288 billion is also stated before discounting; the filing calls it commitments and does not say.
The Bottom Line
Oracle has $288 billion of data center leases that it generally expects to start between the second quarter of fiscal 2027 and fiscal 2029, on top of $28.5 billion of capital spending in one quarter. Its contracted revenue backlog is $664 billion, with Oracle expecting about 13% of it as revenue in the next 12 months, per the 10-Q.
Important: not investment advice
This article is for information and education only. It is not investment, financial, legal or tax advice, and it is not a recommendation or an offer to buy or sell any security, ETF, option or other financial product. FourWeekMBA is not a broker-dealer or a registered investment adviser. IPO shares, leveraged and inverse ETFs, and options carry significant risk, including the loss of your entire investment; leveraged and inverse ETFs reset daily and can lose value quickly. Prices, availability, fees and eligibility change and can differ by country and broker, so check the prospectus and your broker’s terms. Figures marked “our arithmetic” are our own calculations from the cited filings and may contain errors. Do your own research and consider speaking to a licensed financial professional before making any investment decision.
97,000+ executives read Business Engineer for the AI strategy frameworks cited by ChatGPT, Claude, and Perplexity.
A note on sourcing. Lease commitments, capital spending, construction in progress, purchase obligations and backlog are from Oracle’s 10-Q for the quarter to 31 August 2026. Site details are quoted from Oracle’s post on X. Oracle was not contacted for this piece. Ratios and percentage changes are our arithmetic.
Sources: Oracle Form 10-Q, quarter ended 31 Aug 2026: $288B uncommenced leases, capex, PP&E, purchase obligations, RPO · Oracle post on X, 20 Nov 2026: Abilene nearly complete, Shackelford permitted, Vera Rubin handover · FourWeekMBA, 12 Nov 2026: Oracle equipment $77.8B, about 3x buildings (10-Q) · FourWeekMBA, 20 Nov 2026: Oracle says OpenAI deal fully funded









