What Was Posted on X
On 18 October economist Christophe Barraud posted that the US bond market is starting to doubt that the AI infrastructure build-out can be financed under current conditions. Among his examples, he wrote that Cipher agreed to absorb the first $359 million of cost overruns on one project, and that SB Energy needs around $174 billion of capital to fulfil contracts representing $430 billion of future revenue without having completed a data centre. Those figures are his.
AirTrunk, the Blackstone-backed data centre operator, is delaying its planned initial public offering in Singapore, according to a Wall Street Journal headline on 13 October 2026. Bloomberg reported the same day that the company is said to be delaying a $1.5 billion IPO. Both articles are paywalled, and we read only their headlines.
The reports came four days after Firmus, the Nvidia-backed builder of AI data centres, withdrew its application to list on the ASX, ABC News reported on 9 October 2026. Firmus cited recent market volatility and conditions.
Update, 14 October: Why AirTrunk Is Waiting
CNBC-TV18 reported on 13 October 2026 that AirTrunk is delaying the initial public offering of a real estate investment trust in Singapore until next year as higher interest rates and market volatility temper investor demand, according to people familiar with the matter. The Blackstone-backed company had been planning to start formally gauging investor interest for the $1.5 billion REIT IPO at the start of October, the people said.
To sweeten the deal, AirTrunk had considered offering a roughly 6% yield for its REIT, up from a previously envisaged 5.5%, CNBC-TV18 reported, citing the same people; Bisnow attributes the same yield detail to Bloomberg. September’s interest rate rise in the US and the prospect of further increases mean investors are still cautious, they said, and AirTrunk’s deliberations over the size and timing of the potential IPO are ongoing. The report added that Singapore’s main REIT index has fallen 12% since late July, and that the data centre subsidiary of PLDT said last week it would defer its own REIT IPO to next year.
The same report described the Firmus float as having failed to bring in enough demand at the valuation it sought, “reflecting growing investor caution about artificial intelligence infrastructure deals that hinge on future earnings.” It said Dow Jones Newswires had reported earlier that AirTrunk was delaying the listing because of market volatility and uncertainty over US rates. Representatives for AirTrunk did not respond to requests for comment, and Blackstone declined to comment, according to the report.
What Firmus Said
According to ABC News, Firmus said the offer would not appropriately reflect its long-term growth prospects, and that it would pursue private market funding while considering other options. “We will provide additional information to shareholders as those options progress,” the company said in a statement.
ABC reported that the float was set to be the biggest on the Australian share market since Telstra in 1997. The company’s co-chief executives, Oliver Curtis and Tim Rosenfield, targeted a A$44 billion valuation, ABC said, at a sale price of A$11 a share, and the day before the withdrawal reports emerged that the price could be lowered to A$8.25.
Nvidia has a 7.2 per cent stake in Firmus, ABC reported. Firmus’s website lists seven AI factories across Australia, Singapore, Indonesia and Malaysia, two of them operational and five under development, according to the same report.

Business Pill · FINANCIAL CONDITIONS
A one-minute explainer of financial conditions: how easy or costly it is to borrow, and why that matters for companies funding large investments with debt. It teaches the general idea only and says nothing about any company in this story.
The key insight: As we read it, both deals test the same thing: whether public investors will fund AI data centres on the terms their builders want. In the Firmus case ABC reported, the objection was the price and the debt, not demand: Pearce called the story compelling and the valuation not.
Why Investors Held Back
UniSuper chief investment officer John Pearce told ABC the capital raise would be about A$7 billion, giving Firmus a total market value of around A$44 billion. “We think that Firmus indeed has a compelling story. It just doesn’t have a compelling valuation,” he said.
Pearce added that UniSuper was “quite concerned that Firmus will have to keep coming back to the market for a lot more debt and more equity to fund its expansion plans.”
Morningstar senior market strategist Lochlan Holloway wrote that “The neo-clouds are heavily geared,” ABC reported, adding: “The model is to borrow against customer contracts to buy chips, then use the rent to repay the loans.”
Once its data centres are built, Firmus expects to carry about US$30 billion of debt, ABC reported, about six times the US$5 billion of operating earnings it forecasts for 2028.
What Is Reported About AirTrunk
The Wall Street Journal’s headline on 13 October 2026 read: “Blackstone-Backed Hyperscale Data-Center Operator Delays Singapore IPO”. MarketScreener’s summary headline the same morning named the company: “AirTrunk to delay Singapore IPO, WSJ reports”.
Bloomberg’s headline was “Data Center Operator AirTrunk Is Said to Delay $1.5 Billion IPO”. The headline says AirTrunk “is said to” delay the IPO and does not name the source.

The AI Data Centre IPO Pipeline
The two deals sit in a wider queue of data centre and neocloud listings this publication has covered: DayOne’s US IPO filing, which showed 69% of revenue from one customer, and Nscale’s IPO drafts, the first of which named ByteDance.
As we read the Firmus case, the investor objections ABC reported were about the financing model rather than demand for AI capacity: Pearce called the story compelling but the valuation not, and Holloway described the model as borrowing against customer contracts to buy chips.
Update, 18 October: Three Listings Pulled or Paused in a Week
Reuters reported on 15 October 2026 that, in the past week alone, as AI-related stocks weakened and the debt of data-centre operator CoreWeave slumped towards distressed prices, listings for a Blackstone-backed AirTrunk REIT, Nvidia-backed Firmus and SoftBank-backed SB Energy have either been pulled or paused. “The conversation has shifted from growth at any cost to a much sharper focus on quality,” Harry Evans, a partner at law firm Freshfields, told Reuters.
The money has not left the sector, Reuters reported. M&A involving Asian data centres reached $21.3 billion as of that Tuesday, according to Dealogic data, more than double the $10 billion recorded in all of 2025, and syndicated loans and bond issuance for the sector total $22.3 billion so far this year. Equity capital market fundraising is the part that has slowed: $5.4 billion so far this year, a 4.6% drop from the same period in 2025. AirTrunk, despite postponing its REIT listing, is nearing a deal to sell its Johor data centre in Malaysia to a group of investors including local pension fund KWAP at a valuation of about $1 billion, according to two people familiar with the matter cited by Reuters; Blackstone declined to comment and KWAP said it was not in a position to comment.
The Structural Read
Firmus’s own numbers, as ABC reported them, show the scale of the borrowing: about US$30 billion of debt once its data centres are built, against US$5 billion of operating earnings forecast for 2028.
Holloway’s description of the neocloud model, borrowing against customer contracts to buy chips and repaying from the rent, is why an IPO matters to these companies: equity sits underneath that debt.
As we read it, a withdrawn float and a delayed one in the same week move the next financing decision to private markets, which is where Firmus said it would now go.
Lochlan Holloway, Morningstar, as reported by ABC News
“The model is to borrow against customer contracts to buy chips, then use the rent to repay the loans.”
Three Implications
FIRMUS ABC reported that Firmus withdrew its ASX listing application, citing market volatility and conditions, and will pursue private market funding while considering other options.
AIRTRUNK WSJ and Bloomberg headlines on 13 October 2026 say the Blackstone-backed operator is delaying its Singapore IPO; Bloomberg’s headline puts it at $1.5 billion.
NEOCLOUD INVESTORS UniSuper’s Pearce told ABC he was concerned Firmus would have to keep coming back to the market for more debt and more equity to fund its expansion plans.
The Business Engineer Lens
This story maps onto the Business Engineer framework The AI Capex Map.
The framework puts it this way: “The thesis: the capex race is no longer a corporate spending cycle. It is a sovereign-scale financing problem dressed in tech-company clothing — and the financial architecture is starting to invert.”
As we read it, a data centre builder that expects debt of about six times its forecast earnings, and then cannot list at its target price, is that financing problem showing up in the equity market.
What Is Not Established
The reason for AirTrunk’s delay and the move to next year come from CNBC-TV18’s report (Bisnow attributes the same details to Bloomberg), which cites unnamed people familiar with the matter; AirTrunk has not confirmed them. A new date, size or yield for the REIT IPO is not established. We did not read the Wall Street Journal’s articles, including its 14 October report on the Firmus float and the AI trade.
AirTrunk did not respond to requests for comment and Blackstone declined to comment, according to CNBC-TV18. Firmus’s statement is as ABC News reported it; the size and terms of any private funding Firmus pursues are not established in that report.
The Bottom Line
AirTrunk is delaying its planned Singapore IPO, according to Wall Street Journal and Bloomberg headlines on 13 October 2026, with Bloomberg putting the deal at $1.5 billion. Four days earlier, Firmus withdrew its ASX listing application, citing market volatility and conditions, after investors questioned a valuation of about A$44 billion and a model built on borrowing against customer contracts, ABC News reported.
95,000+ executives read Business Engineer for the AI strategy frameworks cited by ChatGPT, Claude, and Perplexity.
A note on sourcing. The AirTrunk report first rested on the headlines of the Wall Street Journal and Bloomberg articles of 13 October 2026 and MarketScreener’s summary headline. On 14 October we added CNBC-TV18’s report of 13 October, read in full, and Bisnow’s report, which attributes the same delay, yield and rate details to Bloomberg; the Bloomberg and Wall Street Journal articles themselves were not read. On 18 October we added Reuters’s analysis of 15 October 2026 (Yantoultra Ngui, Kane Wu and Clare Jim), read in full as reproduced on X; the Dealogic figures and the Johor sale are as Reuters reported them. The Firmus account is from ABC News’s report of 9 October 2026, read in full on 13 October 2026, including Firmus’s statement as ABC reported it. Australian-dollar figures are marked A$. Nothing here is a forecast, and nothing here is financial or investment advice.
Sources: ABC News: Data centre operator Firmus pulls blockbuster ASX float after lacklustre demand (9 Oct 2026) · Bloomberg: Data Center Operator AirTrunk Is Said to Delay $1.5 Billion IPO (13 Oct 2026) · CNBC-TV18 via TradingView: AirTrunk to delay IPO says report (13 Oct 2026) · Bisnow: Blackstone-Backed Data Center Firm AirTrunk Reportedly Delaying $1.5B IPO (13 Oct 2026) · Reuters: Market selloff, rising rates test AI data centre deal boom (15 Oct 2026)