Ulsan AI Data Center 71% Built; Lee Says Speed Is Crucial

SK Group’s AI data center in Ulsan, built with Amazon Web Services, is 71% complete, a site manager from SK Ecoplant told President Lee Jae-myung on his visit on 21 November, Seoul Economic Daily reported. About 900 people work on the site, Lee said he had been told.

“Speed is a matter of life and death,” Lee said, per the same paper. The project was announced in June 2025 at about 7 trillion won ($5.11 billion) for 103 megawatts and 60,000 GPUs (JoongAng Daily). It is on our AI data centre map; AWS is tracked on our Amazon stock page.

Business Pill · Operating Leverage

An evergreen Business Engineer explainer. It teaches the general idea only and does not discuss this project.

The key insight: The SK-AWS Ulsan AI data center is 71% complete with about 900 workers on site, per reports of President Lee’s 21 November visit; its announced 7 trillion won for 103 megawatts is about $49.6 million per megawatt (our arithmetic).

What Lee Said on the Site

“AI data centers are a major source of demand for semiconductors and key infrastructure behind physical AI,” Lee said, per The Korea Times. He added that “when the world is under a heated race, speed is crucial.”

He also raised the workforce. “From the reports I receive overall, they say labor is in very short supply for these advanced facility projects,” he said, adding that ministries would consider how to prepare that workforce (Seoul Economic Daily).

A presidential deputy spokesperson said Lee agreed that “demand for AI data centers and memory chips will increase further as technology develops.” That is the demand SK hynix describes in our memory sold-out piece.

The Ulsan site was 71% complete on 21 November, 449 days after groundbreaking (Seoul Economic Daily, SK Teleco
The Ulsan site was 71% complete on 21 November, with 29% still to build, 449 days after groundbreaking (Seoul Economic Daily, SK Telecom; our arithmetic).

The Project in Numbers

SK Group and AWS signed a 15-year deal on 20 June 2025 for an AWS AI Zone in Ulsan, with SK leading construction, per SK Telecom. Ground was broken on 29 August 2025, 449 days before this visit (our arithmetic).

At 7 trillion won for 103 megawatts, the build works out to about 68 billion won, or about $49.6 million, per megawatt, and about 583 GPUs per megawatt (our arithmetic on the announced figures).

Bar chart: about 900 workers on the Ulsan site today vs up to 78,000 jobs SK Telecom projected over time
About 900 workers on site now, per President Lee, against up to 78,000 direct and indirect jobs SK Telecom projected over time (Seoul Economic Daily, SK Telecom).

Seoul Economic Daily says the site is set to start operating at the end of 2027 and is expected to be the starting point for SK Group’s plan for 5-gigawatt-class AI data centers. SK Telecom said the project could create up to 78,000 direct and indirect jobs over time.

The US Angle

AWS is a US company building this capacity abroad. On 20 November, President Trump said “We’re not going to allow our companies to build data centers outside of our country,” with a “tremendous tax” if they do, as our piece on his remarks reports. SK Telecom said AWS also plans $5.88 billion of investment in Korea by 2027, separate from the Ulsan figure.

The Structural Read

As we read it, Seoul is treating build speed itself as the competitive edge, not just the size of the site.

As we read it, the project sits awkwardly next to Trump’s remark that US companies should not build data centers abroad.

President Lee Jae-myung, 21 Nov 2026 (Seoul Economic Daily)

“Speed is a matter of life and death”

Three Implications

FOR AWS the Ulsan AI Zone is part of a 15-year deal with SK Group (SK Telecom).

FOR SK GROUP the site is set to start operating at the end of 2027 (Seoul Economic Daily).

FOR WORKERS Lee said labor for advanced facilities is in very short supply (Seoul Economic Daily).

What Is Not Established

The 7 trillion won, 103 megawatts and 60,000 GPUs are the June 2025 announcement figures; the 21 November reports cited here do not restate them. The 900-worker count is Lee’s account of what he was told. Seoul Economic Daily’s English edition is machine-translated from Korean, so quotes may differ slightly from the original.

This Week In The AI Supercycle

AI Lost Its Central Banker, the Lab Oligopoly, and the Future of Open Source

This week’s issue: the Nvidia leadership change, read as the AI build-out losing its central banker: who now finances the GPU landlords, backstops the data centres and sponsors open models, and why two labs are becoming the bank.

Read the full issue →

Business Engineer Framework

The AI Supercycle

The Business Engineer map of who builds, finances and captures value in AI.

Read the Map of AI →

The Bottom Line

The SK-AWS Ulsan AI data center is 71% built with about 900 workers on site, per Korean press reports of Lee’s 21 November visit; at the announced 7 trillion won for 103 megawatts, that is about $49.6 million per megawatt (our arithmetic).

97,000+ executives read Business Engineer for the AI strategy frameworks cited by ChatGPT, Claude, and Perplexity.

A note on sourcing. The visit, quotes, 71% figure and worker count come from Seoul Economic Daily and The Korea Times reports of 21 November. The project’s cost, capacity and GPU count are from the June 2025 announcement as reported by Korea JoongAng Daily; the deal terms and AWS’s Korea plan are from SK Telecom’s release. Per-megawatt figures are our arithmetic.

Sources: Seoul Economic Daily, 21 Nov 2026: Lee Visits SK AI Data Center in Ulsan, Says Speed Is Key to Global Race · Seoul Economic Daily, 21 Nov 2026: Lee Pushes Renewable Power for AI Industry on Visit to SK Data Center · The Korea Times, 21 Nov 2026: Lee visits AI data center construction site in Ulsan · Korea JoongAng Daily, 22 Jun 2025: Korea looks to plug into the global AI race with $5 billion Ulsan data center · SK Telecom newsroom, 22 Jun 2025: SK Group and AWS AI Zone in Ulsan

Scroll to Top
FourWeekMBA