ING, SocGen Offer Up to $800M of Data Center Debt, FT Says

ING Bank and Société Générale “have put as much as $800mn of data centre debt up for sale in recent weeks”, including loans tied to Oracle’s Stargate initiative with OpenAI, the Financial Times reported on 17 November, citing people familiar with the matter. The FT says banks that lent to the AI build-out are “seeking to rein in their risk exposure” after Democrats’ sweep of the US midterm elections.

Add HSBC’s roughly $300 million sale of a slice of the Oracle-tied New Mexico loan, which Bloomberg reported on 16 November and our HSBC piece covered, and three European banks have offered or sold about $1.1 billion of data center loans in recent weeks, by our count from the two reports.

Business Pill · Financial Conditions Explained

A one-minute explainer of financial conditions. It teaches the general idea only and does not discuss these loans or any company in this piece.

The key insight: As we read it, the FT report moves the AI debt story from prices to positions: banks are cutting how much they hold, and per the FT some major lenders have stepped out of Anthropic’s $63 billion package over concentrated exposure.

Update, 17 November 2026, 09:13 UTC. An Asian lender says its data center book is small. E.SUN Financial Holding chairman Joseph Huang told the group’s investor conference in Taipei on 17 November that E.SUN’s lending to US AI data centers is only about $500 million and that the exposure is limited, Taiwan’s Anue (cnyes.com) reported. He said this while markets were questioning credit risk in the financial system tied to AI spending.

For scale: E.SUN Bank’s total loans stood at NT$2.98 trillion, up 17% year on year, MoneyDJ reported from the same conference. Our arithmetic: at about NT$33 per dollar, $500 million is roughly NT$16.5 billion, or about 0.55% of that loan book. The European banks above are selling down data center debt; E.SUN is presenting a small, contained position. The reports did not give a breakdown by borrower or loan type. Not investment advice; for information only.

What the FT Reported

Per the FT, ING’s “ongoing auction process includes $500mn of loans linked to data centre operators CyrusOne, EdgeConnex and Vantage Data Centres”, as well as Oracle-backed Project Jupiter in New Mexico. Société Générale “has sought to sell $300mn of project finance debt for Oracle’s Project Lighthouse in Wisconsin and Project Frontier in Texas”.

The FT says “The three projects raised over $56bn in construction debt from dozens of banks last year”. Loans tied to the Wisconsin and Texas projects were “quoted at over 90 cents on the dollar”, which one of the people described as part of “a portfolio management exercise” rather than acute concerns over credit quality. The New Mexico campus, where Oracle recently issued a force majeure notice, “is expected to price in the mid-80s”, the people added.

Data center loans that ING and Société Générale have offered, per the Financial Ti
Data center loans that ING and Société Générale have offered, per the Financial Times on 17 November, and the slice HSBC sold, per Bloomberg on 16 November, in US$ million. The $1.1 billion total is our count of the three reported amounts.

Lenders Step Back From Anthropic

The FT also reports that a “$63bn debt package for Anthropic” and a “$40bn financing” for SpaceX to purchase AI chips are both set to trade in the 144A bond market in the coming months, according to people familiar with the matter. “Some major lenders have dropped out of the Anthropic deal due to concerns around concentrated exposure to the AI lab”, the people said.

The 144A format, per the FT, “allows the debt to be sold on to a broader base of institutional investors”. Our piece on the $63 billion vehicle covered Broadcom’s 26 October release, which said Bank of America, Blackstone, Citi and Morgan Stanley were financing a $63 billion special purpose vehicle to buy Broadcom AI accelerators and lease them to Anthropic; the FT does not name the lenders that dropped out.

Why Banks Are Selling

Don Dimitrievich, global head of energy infrastructure credit at Nuveen, told the FT: “Senior risk officers at many financial institutions have basically indicated that those portfolios need to be reduced”. David Lucking, a structured finance partner at Linklaters, said: “It’s capital-inefficient for banks to just hold on to the debt”.

Hedging is harder, the FT reports, because confidentiality restrictions on some data center loans bar lenders from third-party transactions “including credit default swaps and synthetic risk transfers that require sharing loan information”. Banks have also explored credit insurance and risk-transfer deals to stretch their lending limits, per the FT.

Regulators Ask Questions

The Bank of England is asking UK banks for details of their loans to data centre projects as part of its regular supervisory work, according to a person briefed on the matter, the FT says. The European Central Bank is working on a supervisory review of Eurozone lenders’ exposure to data centre financing, according to people briefed on the matter. ING, Société Générale, the BoE and the ECB declined to comment to the FT.

The report follows Federal Reserve Governor Michael Barr’s 16 November remarks that on-balance-sheet debt of the seven largest AI firms is on course to “exceed $800 billion before year’s end”, as our Fed scenarios piece reported. Our explainer on who holds the risk in AI credit maps the lenders, and every borrowing we follow sits in our AI debt financing tracker.

The Structural Read

As we read the two prices, the market is separating campuses: the FT says the Wisconsin and Texas loans were quoted at over 90 cents, which one person called portfolio management, while the New Mexico campus with the force majeure notice is expected to price in the mid-80s.

As we read the 144A detail, the debt is being moved toward a broader base of institutional investors, which the FT links to lenders growing wary of risk limits to individual borrowers.

Don Dimitrievich, Nuveen, to the Financial Times

“Senior risk officers at many financial institutions have basically indicated that those portfolios need to be reduced”

Three Implications

FOR AI BORROWERS Per the FT, the $63 billion Anthropic package and SpaceX’s $40 billion chip financing are set to trade in the 144A bond market in the coming months.

FOR LENDERS The FT reports that confidentiality restrictions on some data center loans bar credit default swaps and synthetic risk transfers that require sharing loan information.

FOR AI CREDIT WATCHERS Our AI debt financing tracker lists the data center loans we follow, including the HSBC and ING sales.

The Business Engineer Lens

This story maps onto the Business Engineer framework The AI Capex Map & The State of AI Hyperscalers.

The framework says of the AI build-out: “It is a sovereign-scale financing problem dressed in tech-company clothing”.

As we read it, the FT report shows that financing problem reaching bank risk limits: three Oracle projects raised over $56 billion from dozens of banks, per the FT, and lenders are now selling slices. The framework predates the FT report and does not discuss these loans.

What Is Not Established

The loan sales, prices and the Anthropic lender exits rest on people familiar with the matter, as reported by the FT; the FT says some aspects were also reported by Bloomberg and 9fin, which we did not read for this piece. The FT does not give buyers or final sale prices for the ING and Société Générale loans.

The $1.1 billion is our count of three reported amounts: $500 million and $300 million offered, per the FT, and $300 million sold by HSBC, per Bloomberg. It is not a total of bank sales. The ING auction’s $500 million may include the same loans our earlier ING piece described. We did not contact ING, Société Générale, Oracle or Anthropic.

This Week In The AI Supercycle

AI Lost Its Central Banker, the Lab Oligopoly, and the Future of Open Source

This week’s issue: the Nvidia leadership change, read as the AI build-out losing its central banker: who now finances the GPU landlords, backstops the data centres and sponsors open models, and why two labs are becoming the bank.

Read the full issue →

Business Engineer Framework

The AI Capex Map & The State of AI Hyperscalers

The Business Engineer map of AI capex: who spends, who finances it and where the financial architecture is shifting.

Read the Map of AI →

The Bottom Line

Per the FT, ING and Société Générale have put as much as $800 million of data center debt up for sale, Oracle’s New Mexico loans are expected to price in the mid-80s, and some major lenders have dropped out of Anthropic’s $63 billion debt package over concentrated exposure. With HSBC’s sale, that is about $1.1 billion from three European banks, by our count.

95,000+ executives read Business Engineer for the AI strategy frameworks cited by ChatGPT, Claude, and Perplexity.

A note on sourcing. The ING and Société Générale loan sales, their sizes and prices, the 144A plans for the Anthropic and SpaceX financings, the Anthropic lender exits and the BoE and ECB reviews come from the Financial Times report of 17 November 2026 by Michelle Chan and Martin Arnold, which cites people familiar with or briefed on the matter; we read the article in full on ft.com.

The quotes from Nuveen’s Don Dimitrievich and Linklaters’ David Lucking are as given to the FT. HSBC’s sale is Bloomberg’s report of 16 November, the $63 billion vehicle’s lenders are from Broadcom’s 26 October release, and Barr’s figure is from his 16 November speech, all as covered in our earlier pieces. The $1.1 billion is our count. We did not contact ING, Société Générale, Oracle or Anthropic.