Google has halted construction of an AI data centre in southern Belgium after regional officials found a 3-hectare building going up without a valid permit, The Guardian and the BBC reported. The site is in a business park at Aiseau-Presles near Farciennes, about 9 miles west of Charleroi, on a former coal mine.
“Inspectors visited the site and observed that the building was almost finished, with the structural work completed, even though the permit had been refused,” Walloon official Raphaël Stokis told RTBF, The Guardian reported. About 300 workers were on site and were ordered to stop, per Stokis.
Business Pill · Capex and Depreciation
An evergreen Business Engineer explainer. It teaches the general idea only and does not discuss Google or this case.
The key insight: Google paused its Farciennes data centre in Belgium after Walloon inspectors found a 3-hectare building almost finished without a valid permit; the case goes to the Council of State on 7 January.
What Wallonia Says
Wallonia government spokesperson Nicolas Yernaux told Agence France-Presse that a report was being sent to prosecutors alleging “a major offence: the illegal construction of a building covering 3 hectares”, The Guardian reported. RTBF quoted Stokis describing a 30,000-square-metre building with its shell closed. The halt followed an emergency request by Greenpeace, which published drone footage of the works, per Le Soir and The Guardian.
Google said it had paused the works “pending additional guidance” and that “we have operated in Belgium for over 15 years and remain committed to complying with local laws”, per the BBC. Separately it said it was “committed to maintaining an open and collaborative dialogue” with the regional authorities, The Guardian reported.

How the Permit Fell Apart
Google’s 2024 permit covered three smaller air-cooled data centres, and construction started in April 2024 on a campus DCD reported as worth €1bn. In 2025 Google applied to merge two of them into one larger building and switch to liquid cooling, drawing 600 cubic metres of water an hour from the River Sambre, per The Guardian.
That change was approved in April 2026 and appealed by residents, per DCD. In August 2026 Walloon minister François Desquesnes revoked it after a hot, dry summer, noting that Google’s site at Saint-Ghislain uses one billion litres of water a year for cooling, DCD reported. Google filed for annulment and suspension at the Council of State on 17 October, Le Soir reported, and RTBF said the case will only be argued on 7 January.
Google’s Bigger Belgian Bet
Google announced a two-year €5 billion investment in Belgium for 2026 and 2027 in October 2025, to expand its Saint-Ghislain campus and add 300 full-time jobs. The Farciennes dispute sits beside that plan. Fights over local permits are a recurring theme in our coverage, from protesters at a Microsoft site in Amsterdam to Texas’s permit queue.
Our Number
About 5.3 times. At 600 cubic metres an hour, drawn around the clock, the Sambre request would come to about 5.26 billion litres a year, against the roughly one billion litres a year cited for Saint-Ghislain. This is our arithmetic and a theoretical maximum: no source says Google would draw the full amount every hour.

The Structural Read
As we read it, the dispute is less about whether Google builds in Wallonia, where it has a €5 billion plan, than about water: the revoked change would have cooled the site with water from the Sambre.
Three Implications
FOR GOOGLE Its Belgian expansion plan centres on Saint-Ghislain; Farciennes now waits on the Council of State.
FOR REGULATORS Wallonia sent a report to prosecutors alleging a major offence, per its spokesperson.
FOR THE INDUSTRY Water use for cooling was the stated reason the permit change was revoked.
What Is Not Established
Prosecutors have not announced a decision on the report, and the Council of State has not ruled. We have not seen Google say how much it has spent on the Farciennes building, or whether it will change its cooling plan. The €1bn figure is DCD’s 2024 description of the campus, not a figure we have seen Google update.
The Bottom Line
Google kept building after its permit change was revoked, and Wallonia stopped it with the building almost finished. The next date is 7 January at the Council of State.
97,000+ executives read Business Engineer for the AI strategy frameworks cited by ChatGPT, Claude, and Perplexity.
A note on sourcing. Officials’ quotes are as reported by The Guardian, the BBC and RTBF; Le Soir and RTBF passages are our translation from French. The permit history is from DCD and Le Soir. The 5.26 billion litres and 5.3 times are our arithmetic from the reported 600 cubic metres an hour.
Sources: The Guardian, ‘Google told to cease building Belgian datacentre over lack of planning permit’, 27 Nov 2026 · BBC, ‘Google halts illegal construction of Belgian AI data centre’, Nov 2026 · DatacenterDynamics, ‘Construction paused at Google data center in Farciennes, Belgium’, 27 Nov 2026 · Le Soir, 25 Nov 2026 (our translation) · RTBF (our translation) · Google press release, 8 Oct 2025, €5 billion investment in Belgium