Bloomberg reported on 16 November that a $488 million loan for a Malaysian data center project backed by private equity firm Actis “has been delayed while being marketed to other lenders”, citing people familiar with the matter. The data center’s computing capacity will be used by TikTok owner ByteDance, Bloomberg said, and the lead arrangers are HSBC, the Asian Infrastructure Investment Bank, Sumitomo Mitsui Banking Corp and Bank of China.
AIIB’s own project summary gives the scale. For Project Mercury, an Actis-sponsored Malaysian data center implemented by Epoch Digital, it puts the total funding requirement at about $870 million. A $488 million loan is 56% of that, by our arithmetic, close to the 60% ceiling for the loan in AIIB’s plan.
Business Pill · Financial Conditions Explained
A one-minute explainer of financial conditions. It teaches the general idea only and does not discuss this loan or any company in this piece.
The key insight: As we read it, the delay sits at the step where risk leaves the arranging banks: AIIB’s plan funds roughly 60% of Project Mercury with a syndicated loan, so the lender presentation that did not take place on 2 November was the route to spreading that loan beyond its first banks.
What Bloomberg Reported
According to Bloomberg’s people, “A planned online presentation scheduled for Nov. 2 by loan arrangers for other banks invited to participate in the financing by Epoch Digital Pte. Ltd. didn’t take place”. A visit planned for the same week to the data center “also failed to happen”.
The four lead arrangers “have signed the loan and committed to providing Epoch Digital with the funds”, Bloomberg said. The missed steps matter for the next tier of banks: they are “important and standard steps for prospective banks that need to undertake due diligence on the loan before deciding to participate in syndication, and mark a rare postponement”.
The stated cause is scheduling. “Management of Epoch Digital wasn’t available on the scheduled dates, prompting the delay in the syndication timeline”, said one of the people. The presentation and site visit “are being coordinated for new dates”, and the arrangers had reserved the right to amend the timetable at any time, Bloomberg reported.
Actis declined to comment and Epoch Digital did not respond, per Bloomberg. HSBC and SMBC declined to comment; AIIB and Bank of China did not immediately respond.

What AIIB’s Filing Shows
The AIIB summary, dated 24 April 2026, describes a green hyperscale data center in Malaysia with “an initial IT capacity of 60MW within a campus designed for a total IT capacity of 120MW”. It says the first 60MW phase “is fully contracted under an off-take agreement with BytePlus”. The project is sponsored by Actis and implemented by Epoch Digital, an Actis portfolio company; the borrower is Epoch Digital (MYLB) Ltd.
On money, the summary says the roughly $870 million is “to be financed through a syndicated loan facility equal to the lower of USD520 million or 60% of the total project cost, with the remainder funded by equity”. AIIB “proposes to participate in the loan syndication with a size of up to USD125 million”; AIIB approved that financing on 23 April 2026.
The site is in the Nusa Cemerlang Industrial Park within the Nusajaya Tech Park data center cluster, and the summary says that during construction “the Project is nearly completed”. The estimated date of last disbursement is April 2028.
The Numbers, Side by Side
By our arithmetic on the two sources, Bloomberg’s $488 million is $32 million below AIIB’s $520 million loan cap and 56% of the $870 million funding estimate. AIIB’s up to $125 million ticket would be about 26% of a $488 million loan.
Per megawatt, $870 million over the 60MW first phase is about $14.5 million, and $488 million is about $8.1 million, by our arithmetic. AIIB’s summary does not split the $870 million between the first phase and the wider 120MW campus, so the per-MW figures assume it all funds the first 60MW.
How It Fits Other AI Debt Deals
Bloomberg tied the delay to “the complexities around financing the AI buildout”, with lenders that “juggle the flood of borrowing requests against internal exposure limits”. It cited a PricewaterhouseCoopers estimate that data center spending in the Asia-Pacific could reach $8.2 trillion by 2050.
The presentation that did not take place was set for 2 November, the day Bloomberg reported that Singapore’s STTGDC was seeking a $2.4 billion loan, as our STTGDC piece covered. In October, Blue Owl’s Stack sought a $6 billion loan for a Melbourne data center, per our Stack piece.
Elsewhere, banks delayed a bond sale on a $15 billion Anthropic-tied Texas loan, Bloomberg reported on 28 October (our piece), and Reuters reported on 9 November that some lenders balk at AI debt even with backstops. AI data center stocks have lost $4.2 trillion, per our data center stocks piece, and Samsung and SK Hynix lost $93 billion today as the KOSPI fell 3.6%, per our Korea piece. Every borrowing we track sits in our AI debt financing tracker.
The Structural Read
As we read the AIIB file, this is a contracted project rather than a speculative one: the summary says the first 60MW phase is fully contracted under an off-take agreement with BytePlus, and that the project is nearly completed at the construction stage.
As we read Bloomberg’s account, the hold-up sits with the borrower’s calendar rather than the banks’ books: the four lead arrangers have signed and committed, and one person attributes the missed dates to Epoch Digital management not being available.
Asian Infrastructure Investment Bank, Project Mercury project summary, April 2026
“The total funding requirement is estimated at approximately USD870 million, to be financed through a syndicated loan facility equal to the lower of USD520 million or 60% of the total project cost, with the remainder funded by equity.”
Three Implications
FOR THE BORROWER AND SPONSOR Bloomberg reports the $488 million loan is delayed while being marketed to other lenders; AIIB’s summary names Epoch Digital (MYLB) Ltd as borrower and Actis as sponsor.
FOR LENDERS AIIB’s summary says it proposes to take up to $125 million of the syndicated loan, about 26% of $488 million by our arithmetic; our AI debt financing tracker lists the other data center loans we follow.
FOR THE AI BUILD-OUT IN ASIA Our STTGDC piece and Stack piece cover two larger regional data center loans reported by Bloomberg.
The Business Engineer Lens
This story maps onto the Business Engineer framework The AI Capex Map & The State of AI Hyperscalers.
The framework says of the AI build-out: “It is a sovereign-scale financing problem dressed in tech-company clothing”.
As we read it, Project Mercury shows that financing problem one level down, at a single 60MW Malaysian site: equity covers about 40% under AIIB’s plan and a bank syndicate, with a multilateral lender inside it, carries the rest. The framework predates the Bloomberg report and does not discuss this project.
What Is Not Established
Bloomberg’s account rests on people familiar with the matter, and the scheduling reason comes from one of them. The article gives no new dates, no change to the loan’s size or terms, and no figure for how many banks were invited.
Bloomberg does not name the project. Its details (Actis, Epoch Digital, Malaysia, ByteDance as the capacity user, AIIB as a lead arranger) match AIIB’s Project Mercury file, so as we read it this is the same facility, but neither source says so. The 56%, $32 million, 26% and per-MW figures are our arithmetic and depend on that match. We did not contact the companies, the banks or AIIB.
The Bottom Line
Per Bloomberg, the syndication of a $488 million loan for an Actis-backed Malaysian data center used by ByteDance has been delayed after a 2 November lender presentation and a site visit did not take place, with the four lead arrangers already signed. AIIB’s filing for the matching project shows an $870 million build with a loan of up to $520 million and an AIIB ticket of up to $125 million.
95,000+ executives read Business Engineer for the AI strategy frameworks cited by ChatGPT, Claude, and Perplexity.
A note on sourcing. The delay, the $488 million size, the 2 November presentation and the site visit come from Bloomberg’s report of 16 November 2026 by Aileen Chuang and Megawati Wijaya, which cites people familiar with the matter; we read it in full through The Edge Malaysia’s syndication of the Bloomberg article, and its opening on bloomberg.com. Project Mercury’s capacity, offtaker, sponsor, borrower and funding plan come from the Asian Infrastructure Investment Bank’s project page and Project Summary Information (P000938, prepared 24 April 2026), read in full.
Matching the two, and the 56%, $32 million, 26% and per-MW figures, are our arithmetic. Company and bank responses are as Bloomberg reported them; we did not contact Actis, Epoch Digital, ByteDance, the banks or AIIB.
Sources: Bloomberg, 16 Nov 2026 · AIIB, Project Mercury project summary P000938, Apr 2026