595 of 598 Submissions Push Back on Anthropic’s 1.44GW Site

Of nearly 600 public submissions on the proposed Western Downs Digital Park in Queensland, where Anthropic is the anchor tenant, 595 opposed it or asked for a delay, Reuters reported on 20 November, citing a filing for the project.

Two submissions supported the project and one was neutral, the filing said. It would be the AI company’s first Australian facility.

Important: not investment advice

This article is for information and education only. It is not investment, financial, legal or tax advice, and it is not a recommendation or an offer to buy or sell any security, ETF, option or other financial product. FourWeekMBA is not a broker-dealer or a registered investment adviser. IPO shares, leveraged and inverse ETFs, and options carry significant risk, including the loss of your entire investment; leveraged and inverse ETFs reset daily and can lose value quickly. Prices, availability, fees and eligibility change and can differ by country and broker, so check the prospectus and your broker’s terms. Figures marked “our arithmetic” are our own calculations from the cited filings and may contain errors. Do your own research and consider speaking to a licensed financial professional before making any investment decision.

Business Pill · Guardrails Explained

An evergreen Business Engineer explainer on guardrails. It teaches the general idea only and does not discuss this project.

The key insight: Anthropic’s first Australian data centre, a 1.44 GW site in Queensland’s Western Downs, drew 595 objections or delay requests out of 598 public submissions, Reuters reports; only five objections came before Anthropic was named as tenant.

What the Filing Shows

The site is about 250 km west of Brisbane, on farmland. It has a planned computing load of 1.44 gigawatts, which Reuters says would make it one of Australia’s biggest data centres.

The filing was lodged on behalf of developer Zerra DC. It says “a significant number of submissions raise reasonable matters regarding water, power, noise, roads, housing and the scale of the project”.

Objectors mostly cited water use, electricity demand and prices, noise, road damage from construction traffic and pressure on housing, according to Reuters.

About one-third of the submissions came from people living within 200 km of the site, the filing said.

Bar chart: 5 objections in the first month before Anthropic was named as tenant, versus about 593 submissions in the 57 days after, per Reuters
Almost all submissions arrived after the project named Anthropic as its tenant on 15 September (second bar is our arithmetic).
Submissions on the Anthropic-anchored Western Downs Digital Park, as counted in the filing reported by Reuters
Submissions on the Anthropic-anchored Western Downs Digital Park, as counted in the filing reported by Reuters.

The Anthropic Effect

Before the project named Anthropic as its tenant on 15 September, it had received five objections in a month, a log of public comments showed, Reuters reported.

The rest arrived between then and 11 November, when the local government stopped accepting submissions. That window was 57 days (our arithmetic).

Of the 598 submissions counted in the filing, 595 opposed the project or asked for a delay, about 99.5% (our arithmetic on the filing’s figures).

A Wider Backlash

Goodman Group scrapped a roughly A$1.2 billion data centre planned for Sydney in September after a public backlash, Reuters reported. NextDC delayed a Melbourne project amid resident concerns about energy use.

Update, 20 November 2026, 06:45 UTC: NEXTDC says it will not pursue new sites near homes. Australian operator NEXTDC told its annual meeting on 20 November that “given community sensitivities we do not intend to pursue new development opportunities that are near residential properties,” adding that it “only builds data centres on land zoned as industrial,” according to its Chairman and CEO statement released to the market. Bloomberg reported the pledge came after community opposition and power constraints delayed a major expansion.

That project is M3 Melbourne, in an industrial precinct in West Footscray and under development since 2021, according to NEXTDC’s releases; its statement says the delay relates to “the timing of the next increase in power supply to M3” and that the board is working with Jemena on a path forward. The same day NEXTDC raised its FY27 net revenue guidance to A$485 million to A$500 million, still excluding the affected M3 customer contracts; the midpoint is 21.5% below the A$615 million to A$640 million it guided on 27 August (our arithmetic), a gap that largely reflects about A$140 million of M3 revenue the August guidance included and the new one excludes, according to the guidance release.

NEXTDC is not the developer of the Queensland site in this piece: the planning filing was lodged on behalf of Zerra DC. Local pushback is also shaping projects in Texas and Minneapolis.

The pushback is not limited to Australia. In Minneapolis, the mayor vetoed council limits on data centres this week, as we reported, and Texas has resumed data-centre permits before its next governor takes office, as we reported.

The Structural Read

As we read the comment log, attaching a famous AI tenant turned a quiet planning file into a public fight within weeks.

As we read the filing, the issues objectors raised (water, power prices, roads, housing) are the same ones driving data-centre fights in the US.

Filing lodged on behalf of Zerra DC

“A significant number of submissions raise reasonable matters regarding water, power, noise, roads, housing and the scale of the project.”

Three Implications

FOR ANTHROPIC Its first Australian facility now faces opposition from nearly every public submission, per the filing Reuters reported.

FOR DATA-CENTRE DEVELOPERS Reuters cites two earlier Australian setbacks: Goodman’s scrapped Sydney site and NextDC’s delayed Melbourne project.

FOR LOCAL GOVERNMENTS The filing itself calls many of the concerns reasonable: water, power, noise, roads and housing.

What Is Not Established

Reuters notes the submissions are not binding. Representatives of Zerra and Anthropic were not immediately available for comment, it said.

The report does not say when a planning decision is due or what conditions could be attached. We have not read the filing itself, only Reuters’ account of it.

The filing was published the same week Anthropic debuted on Nasdaq, closing its first day at $97.17.

This Week In The AI Supercycle

AI Lost Its Central Banker, the Lab Oligopoly, and the Future of Open Source

This week’s issue: the Nvidia leadership change, read as the AI build-out losing its central banker: who now finances the GPU landlords, backstops the data centres and sponsors open models, and why two labs are becoming the bank.

Read the full issue →

Business Engineer Framework

The AI Supercycle

The Business Engineer map of where value pools in the AI stack and who controls its bottlenecks.

Read the Map of AI →

The Bottom Line

Anthropic’s first Australian data-centre site drew 595 objections or delay requests out of 598 submissions, nearly all after its name was attached, so the 1.44 GW project now heads into a planning process where local opposition is on the record.

Important: not investment advice

This article is for information and education only. It is not investment, financial, legal or tax advice, and it is not a recommendation or an offer to buy or sell any security, ETF, option or other financial product. FourWeekMBA is not a broker-dealer or a registered investment adviser. IPO shares, leveraged and inverse ETFs, and options carry significant risk, including the loss of your entire investment; leveraged and inverse ETFs reset daily and can lose value quickly. Prices, availability, fees and eligibility change and can differ by country and broker, so check the prospectus and your broker’s terms. Figures marked “our arithmetic” are our own calculations from the cited filings and may contain errors. Do your own research and consider speaking to a licensed financial professional before making any investment decision.

97,000+ executives read Business Engineer for the AI strategy frameworks cited by ChatGPT, Claude, and Perplexity.

A note on sourcing. The submission counts, the 1.44 GW load, the developer, the dates and the quoted filing text come from Reuters’ 20 November report on the filing; we did not read the filing itself. The 57-day window and the 99.5% share are our arithmetic on those figures (595 of 595+2+1 = 598).

Sources: Reuters, Anthropic’s Australian data centre overwhelmingly opposed by residents, 20 Nov 2026 (syndicated) · FourWeekMBA, Minneapolis mayor vetoes data-center limits, 20 Nov 2026 · FourWeekMBA, Texas data-center permits resume, 20 Nov 2026