IES Holdings’ Backlog Doubles to $4.96B on Data Center Work

IES Holdings (NASDAQ: IESC) ended its fiscal year with a backlog of about $4.96 billion, up from $2.37 billion a year earlier, according to its earnings release filed with the SEC on 20 November.

That is 2.09 times the year-ago level (our arithmetic). The Houston electrical and infrastructure contractor tied growth in three of its four segments mainly to the data center end market.

IES is one of the contractors wiring the build-out tracked on our AI data centre map. Its numbers show where the money lands on site.

Important: not investment advice

This article is for information and education only. It is not investment, financial, legal or tax advice, and it is not a recommendation or an offer to buy or sell any security, ETF, option or other financial product. FourWeekMBA is not a broker-dealer or a registered investment adviser. IPO shares, leveraged and inverse ETFs, and options carry significant risk, including the loss of your entire investment; leveraged and inverse ETFs reset daily and can lose value quickly. Prices, availability, fees and eligibility change and can differ by country and broker, so check the prospectus and your broker’s terms. Figures marked “our arithmetic” are our own calculations from the cited filings and may contain errors. Do your own research and consider speaking to a licensed financial professional before making any investment decision.

Business Pill · Operating Leverage

An evergreen Business Engineer explainer. It teaches the general idea only and does not discuss this report.

The key insight: IES Holdings’ backlog reached $4.96 billion, 2.09 times a year earlier (our arithmetic), as data center work lifted three of its four segments; DBM Global adds $2.6 billion more.

What IES Reported

Fourth-quarter revenue rose 55% to $1.39 billion, from $898 million. Operating income rose 108% to $217.2 million, from $104.3 million.

Diluted earnings per share were $4.50, against $2.49 a year earlier. Adjusted diluted EPS, a non-GAAP measure, was $4.07, against $1.88.

For fiscal 2026, which ended 30 September, revenue rose 33% to $4.48 billion. Operating income rose 58% to $605.7 million, and diluted EPS was $13.24.

Communications backlog rose about 2.85 times in a year (our arithmetic on IES Holdings’ filing).
Communications backlog rose about 2.85 times in a year (our arithmetic on IES Holdings’ filing).

Data Centers Carried Three Segments

Communications revenue rose 48% to $1.69 billion, which IES linked to “continuously increasing demand” from data center customers. Segment operating income rose to $290.0 million, from $166.5 million.

Commercial & Industrial revenue rose 83% to $799.5 million, driven mainly by data center work, IES said. Its operating income more than tripled to $163.1 million, from $47.3 million.

Infrastructure Solutions revenue rose 66% to $826.6 million, primarily for the data center end market. Operating income rose to $194.4 million, from $118.5 million.

Together, those three segments brought in $3.31 billion, about 74% of total revenue (our arithmetic).

Bar chart of IES Holdings fiscal 2026 operating income by segment: Communications $290.0m, Infrastructure Solutions $194.4m, Commercial and Industrial $163.1m, Residential $40.1m
IES Holdings’ three data-center-linked segments earned $647.5 million in fiscal 2026; Residential earned $40.1 million.

Housing Went the Other Way

Residential revenue fell 7% to $1.22 billion, which IES blamed on housing affordability, high mortgage rates and insurance costs. Its operating income fell about 61% to $40.1 million, from $103.8 million (our arithmetic).

The Backlog Behind the Growth

Communications backlog reached $2.15 billion, up from $756 million a year earlier, about 2.85 times (our arithmetic). Remaining performance obligations, the GAAP measure, totalled $3.48 billion.

Backlog is a non-GAAP figure that also counts signed agreements and letters of intent IES cannot yet enforce. Those made up about $1.47 billion of the total.

The $4.96 billion excludes DBM Global, the structural steel company IES bought on 5 October. IES said the deal added $2.6 billion of backlog and about 4,000 employees.

Debt, Buybacks and DBM Global

IES ended the year with $155.1 million in cash, $288.9 million of marketable securities and no debt. It then expanded its credit line to $700 million and borrowed $525 million for DBM Global, repaying $125 million by 19 November.

After the year ended, IES bought back 350,000 shares at an average $248.00. Executive Chairman Jeff Gendell said it used “stock market disruptions” in its industry to do so.

The board authorized another $350 million for buybacks on 19 November.

The Structural Read

As we read it, IES shows the AI build-out paying the electricians and steel fabricators, not only the chipmakers.

As we read it, buying back stock at $248 during an industry sell-off signals management sees the backlog as durable.

Matt Simmes, IES Holdings CEO (20 Nov 2026)

“With record levels of backlog at September 30, 2026, we expect continued strong organic growth in fiscal 2027 in our Communications, Commercial & Industrial and Infrastructure Solutions segments.”

Three Implications

FOR DATA CENTER BUILDERS Communications backlog was $2.15 billion at 30 September, per IES.

FOR IES SHAREHOLDERS The board added $350 million to the buyback on 19 November.

FOR HOUSING Residential operating income fell to $40.1 million from $103.8 million, per IES.

What Is Not Established

The release gives no fiscal 2027 revenue or earnings guidance. It also does not say how much revenue came from data centers as a share of the total, or name customers.

This Week In The AI Supercycle

AI Lost Its Central Banker, the Lab Oligopoly, and the Future of Open Source

This week’s issue: the Nvidia leadership change, read as the AI build-out losing its central banker: who now finances the GPU landlords, backstops the data centres and sponsors open models, and why two labs are becoming the bank.

Read the full issue →

Business Engineer Framework

The AI Supercycle

The Business Engineer map of who builds, finances and captures value in the AI build-out.

Read the Map of AI →

The Bottom Line

IES Holdings’ backlog roughly doubled to $4.96 billion, before DBM Global’s $2.6 billion. Quarterly operating income rose 108%, while its housing business shrank.

Important: not investment advice

This article is for information and education only. It is not investment, financial, legal or tax advice, and it is not a recommendation or an offer to buy or sell any security, ETF, option or other financial product. FourWeekMBA is not a broker-dealer or a registered investment adviser. IPO shares, leveraged and inverse ETFs, and options carry significant risk, including the loss of your entire investment; leveraged and inverse ETFs reset daily and can lose value quickly. Prices, availability, fees and eligibility change and can differ by country and broker, so check the prospectus and your broker’s terms. Figures marked “our arithmetic” are our own calculations from the cited filings and may contain errors. Do your own research and consider speaking to a licensed financial professional before making any investment decision.

97,000+ executives read Business Engineer for the AI strategy frameworks cited by ChatGPT, Claude, and Perplexity.

A note on sourcing. All figures are from IES Holdings’ fiscal fourth-quarter earnings release, filed as Exhibit 99.1 to its 8-K with the SEC on 20 November 2026. Backlog is a non-GAAP measure as defined by IES. The 2.09x and 2.85x backlog multiples, the 74% share of revenue from the three data-center-linked segments ($3,314.6m of $4,477.9m) and the 61% fall in Residential operating income are our arithmetic.

Sources: IES Holdings, Reports Fiscal 2026 Fourth Quarter and Full Year Results (8-K Exhibit 99.1), 20 Nov 2026 · SEC EDGAR filing index, IES Holdings 8-K, 20 Nov 2026 · FourWeekMBA AI data centre map