Voters in dozens of US counties and cities will soon have the chance to help enact policies that would slow down the development of data centers, Bloomberg reported on 2 November. Municipalities from Nevada to Georgia are giving residents a chance to vote on policies that would tax, regulate or even ban artificial intelligence infrastructure, according to Bloomberg, which named Meta Platforms and the developer Applied Digital among the companies that could be affected.
Ballotpedia, which tracks local ballot measures, lists at least 50 data center-related local measures in 13 states in 2026, with 41 of them on the ballot on 3 November. By our count of Ballotpedia’s list, those 41 measures sit in 10 states, and Ohio has 21 of them.
Results update (02:47Z, 4 Nov). Partial: these local measures are counted by local election offices, not called by AP. Between 02:22Z and 02:42Z we found returns on official pages for 9 of the 41 measures, and only one page showed all precincts reporting. In Edgewater, Florida, the Volusia County elections page, read at 02:26Z on 4 November, shows Amendment 4, which would prohibit new data centers, at Yes 7,856 (77.22%) and No 2,317 (22.78%), labelled unofficial, with the county-wide status at 156 of 156 precincts reported. Results are not certified.
By our count from official pages as of 02:42Z: of the 21 ban-or-pause measures, 1 was passing (Edgewater), 1 had partial returns and 19 were not read, not posted or not checked; of the 7 rules-or-review measures, 2 had partial returns and 5 were not read, not posted or not checked; of the 13 allow-or-back measures, 5 had partial returns and 8 were not read, not posted or not checked. Grouping is ours; results are not certified. Ohio detail is in our Ohio piece.
Results from AP race calls and official election offices; uncalled races are marked uncalled. This box will be updated.
The key insight: Ballotpedia lists 41 data center-related local measures on the 3 November ballot, and by our count of its list Ohio has 21 of them; in the six such measures voters decided earlier in 2026, Ballotpedia says the side favoring limits on data center development won each time.
What Is on the Ballot
The 3 November measures are not all of one kind. Grouping them by what a yes vote would do, based on Ballotpedia’s description of each measure, we count 21 that would ban or pause data centers, 7 that would add rules or a review, and 13 that would allow or back data center development.
Several Ohio measures set a power threshold. Ballotpedia describes measures in Conneaut, Defiance and Oregon that would prohibit data centers with demand above 25 megawatts, and Ottawa, Kansas, has a measure that would prohibit data centers that use more than 25 megawatts of power.
Others run the other way. In Madison County, Illinois, four township measures would advise officials to permit the construction and operation of new data centers, according to Ballotpedia. In Wilmington, Ohio, four referendums ask voters whether to uphold rezonings from rural residential to light industrial, and in Boulder City, Nevada, a measure would allow data centers within the Eldorado Valley Transfer Area.
Perry, Ohio, has a measure that would require hyperscale data center developers seeking special tax incentives to provide financial guarantees. In Grove City, Ohio, a measure would require voter approval for certain large developments, Ballotpedia says.
Business Pill · Grid Cost Allocation Explained
An evergreen Business Engineer explainer on how the cost of grid upgrades is split between large new loads and existing customers. It explains the general idea only and does not discuss these ballot measures.

What Earlier Votes Showed
As of 30 October, voters had decided six data center-related measures in 2026, Ballotpedia says, and in each case a majority favored greater limits on data center development, either by approving new restrictions or by rejecting a measure that would have supported development.
Ballotpedia’s vote counts for those six show the winning side took between 66% and 90% of the vote. In Monterey Park, California, 88% voted yes in June to amend the land use element to prohibit data centers. In Augusta Township, Michigan, 90% voted against upholding a rezoning for a proposed data center in August.
The lowest margin among the six was in Port Washington, Wisconsin, where 66% voted in April to require voter approval before the city creates certain tax incremental districts. In Nottingham, New Hampshire, 90% voted in September for a 12-month stop on data center permits.
Update, 2 Nov: data centres came up at a Brooklyn midterm event, TechCrunch reported. TechCrunch reported on 31 October from a midterm event hosted by the media company Newsreel in a Brooklyn warehouse, five days before the vote. Its reporter, who moderated a panel on data centres there, wrote that AI and data centres came up in nearly every conversation. The report does not name a Brooklyn race, a New York candidate campaigning on data centres or a specific data centre proposal. New York is not among the 10 states on the Ballotpedia list of measures in this piece; TechCrunch wrote that it is among the states considering more guardrails and transparency around data centre development. Newsreel founder Jack Brewster told TechCrunch the topic “came up in every conversation on stage, and it was the second most common topic in the questions people sent us when they RSVP’d.” TechCrunch also cited Data Center Watch. Its quarterly reports count at least 75 data centre projects worth about $130 billion blocked or delayed by local opposition in the first quarter of 2026, and at least 45 projects worth nearly $68 billion in the second quarter. By our arithmetic, that is at least 120 projects and about $198 billion in the first half of 2026.
Connecting the Coverage
On 1 November we counted that midterm pause pledges cover 30 GW of 2028 data centers. Earlier today we reported that Norway is weighing a data center freeze, with Virginia residents fighting proposed sites in Goochland County.
In Georgia, OpenAI pledged more than $20 million for wetlands ahead of a county site-plan vote also due on Tuesday. That is a county board vote, not a ballot measure. Ballotpedia’s list of data center ballot measures includes none in Georgia.
The Structural Read
As we read Ballotpedia’s list, the fight is mostly local and mostly in one state: Ohio’s 21 measures are more than the other nine states combined, by our count.
As we read the descriptions, a 25-megawatt line recurs: measures in Conneaut, Defiance and Oregon, Ohio, and in Ottawa, Kansas, would prohibit data centers above that level of demand, which leaves smaller sites outside the ban.
Ballotpedia, on the six measures decided as of 30 October
“In each case, a majority of voters favored greater limits on data center development”
Three Implications
FOR DATA CENTER DEVELOPERS Bloomberg names Meta Platforms and the developer Applied Digital among the companies that could be affected by the local votes.
FOR LOCAL TAX DEALS In Perry, Ohio, a measure would require hyperscale data center developers seeking special tax incentives to provide financial guarantees, Ballotpedia says.
FOR LAND ALREADY REZONED In Wilmington, Ohio, four referendums ask voters whether to uphold rezonings from rural residential to light industrial, according to Ballotpedia.
The Business Engineer Lens
This story maps onto the Business Engineer framework The State of AI Data Centers.
The framework reads: “The structural bottleneck isn’t computing, it’s electrons.”
As we read it, these ballot measures add a local layer to that bottleneck: several would cap data centers by megawatts of demand. The framework is the owner’s argument and does not discuss these ballot measures.
Related coverage: Morgan Stanley’s net US data center power gap hits 43 GW · OKC approves a data center with a 55 dB cap as towns pause
What Is Not Established
Bloomberg’s full list of places is behind its paywall; we read only its opening, so our count rests on Ballotpedia’s list, which Ballotpedia says covers at least 50 measures. Some measures, such as zoning referendums, do not name data centers in their titles; Ballotpedia includes them as data center-related. Grouping the 41 by what a yes vote would do is our reading of Ballotpedia’s descriptions.
The Bottom Line
Ballotpedia lists 41 data center-related local measures on the 3 November ballot; by our count they span 10 states, and Ohio has 21 of them.
By our grouping, 21 would ban or pause data centers and 13 would allow or back them. In the six measures already decided this year, Ballotpedia says the side favoring limits won each time.
95,000+ executives read Business Engineer for the AI strategy frameworks cited by ChatGPT, Claude, and Perplexity.
A note on sourcing. Bloomberg is cited from the readable opening of its 2 November report. Measure counts, descriptions and earlier results come from Ballotpedia’s data center ballot measure tracker, read on 2 November. The state count, the Ohio share and the three-way grouping are our own reading of that list.
Sources: Bloomberg, 2 Nov 2026 · Ballotpedia, Data center-related ballot measures, 2026