OpenAI Pledges $20M+ for Wetlands Ahead of Georgia Site Vote

Effingham County commissioners in Georgia are scheduled to vote on Tuesday, 3 November, on the site plan for Project Camellia, the data center campus that OpenAI is developing in Effingham County, according to the county’s meeting agenda and the Savannah Morning News. The county staff report attached to the agenda describes six data center buildings on about 1,347 acres, with 1,608 parking spaces. An OpenAI spokesperson told the paper the company is committing more than $20 million to wetland mitigation.

The staff report says county rules require one parking space for every two employees and that employee counts have not been provided. By our arithmetic, 1,608 spaces is what that ratio would require for 3,216 workers, about three times the more than 1,000 positions an OpenAI spokesperson told the Savannah Morning News the company anticipates. That figure is a parking calculation, not a job forecast.

The key insight: Effingham County’s staff report for Tuesday’s vote describes six data center buildings on about 1,347 acres with 1,608 parking spaces; under the county’s one-space-per-two-employees rule that is the parking required for 3,216 workers by our arithmetic, a parking calculation rather than a job forecast.

What Is on Tuesday’s Agenda

The Board of Commissioners’ agenda for its 5 p.m. meeting on 3 November lists the item as number 16. It is an application by Octans GA LLC for a site plan for “Project Camellia,” a proposed data center development along Effingham Parkway and Gateway Parkway, on land zoned I-1 (industrial). The Effingham Herald has described Octans GA LLC as the OpenAI affiliate named as a defendant in a lawsuit over the project, as we reported on 28 October.

The staff report lists two parcels of about 739.95 and 607.19 acres, which by our arithmetic add up to about 1,347 acres. It names six data center buildings, DC01 to DC06, each about 42 feet tall, plus a warehouse of about 100,000 square feet, an operations building of about 75,000 square feet, chiller equipment for cooling and three electrical substations with supporting electrical yards.

The plan provides 250 parking spaces for each data center building and 54 each for the warehouse and the operations building, according to the report. It includes 300-foot buffers next to agricultural-residential land, 150-foot buffers next to commercial land and 25-foot buffers next to other industrial land. County staff concluded that the site plan meets the applicable zoning and site plan requirements of the industrial district, including parking, buffering and access standards.

Project Camellia's 1,608 planned parking spaces against the job figures OpenAI has given. Sources: Effingham C
Project Camellia’s 1,608 planned parking spaces against the job figures OpenAI has given. Sources: Effingham County staff report for the 3 November 2026 site-plan vote (1,608 spaces; one space per two employees); Savannah Morning News, 2 November 2026 (OpenAI spokesperson, more than 1,000 positions); OpenAI’s Project Camellia FAQ as reported by FourWeekMBA on 28 October (400 permanent jobs at the start). 3,216 is our arithmetic (1,608 x 2) and is not a job forecast.

What OpenAI Says

The vote was originally scheduled for September, the Savannah Morning News reported. “We agreed to a postponement to allow a more substantial review,” a spokesperson for OpenAI told the paper.

The spokesperson said the site is designed to avoid 70% of the wetlands on the property. “We’re committing more than $20 million to mitigation through federally approved wetland conservation banks that serve the project area,” the spokesperson said, according to the paper. The county staff report notes that its GIS mapping shows wetlands and FEMA Zone AE floodplain areas on portions of the site.

Business Pill · Grid Cost Allocation Explained

An evergreen Business Engineer explainer on how the cost of grid upgrades is split between large new loads and existing customers. It explains the general idea only and does not discuss Project Camellia.

The Concerns in the Regional Review

The staff report includes findings from the Development of Regional Impact review, completed on 26 August 2026. The Coastal Regional Commission strongly advised the applicant to evaluate the project’s effects on drainage and flood risk, given the FEMA flood zone designation.

On water, the City of Savannah said it anticipates only briefly providing the initial phase of the project’s water demand, through wholesale surface water to Effingham County, before a new Effingham County surface water treatment plant comes online in early 2030, according to the report. Georgia’s Wildlife Resources Division suggested consulting the US Fish and Wildlife Service about federally listed species documented near the project.

Savannah Riverkeeper raised concerns about water use, stormwater runoff, energy demand and construction timelines, the report says. One Hundred Miles, a coastal advocacy group, questioned the energy supply and transmission the project needs and where its backup power would come from. The group wrote that the operational “flexibility” during peak demand hours lacked specific details on grid resilience with Georgia Power, according to the Savannah Morning News.

Connecting the Coverage

On 28 October we reported in Suit targets OpenAI Georgia deal carrying $900M tax break that plaintiffs, including One Hundred Miles, had asked a judge to void agreements tied to the project. According to the plaintiffs’ filing as reported by the Effingham Herald, one agreement included nearly $900 million in tax abatements. The Herald describes the campus as a $20 billion project, and OpenAI says it is contracting with Georgia Power for 3.2 gigawatts of power. What’s new: the site plan’s building, acreage and parking figures, and Tuesday’s vote.

OpenAI’s push to rename such sites is in OpenAI plans to rebrand data centers ‘AI compute campuses’; the county documents call Project Camellia a data center. Local fights over data centers are in Midterm pause pledges cover 30 GW of 2028 data centers, OKC approves a data center with a 55 dB cap and Arizona data center’s well permit. The national power picture is in our piece on the 43 GW net US data center power gap.

The Structural Read

As we read the staff report, the county’s site-plan test is narrow: zoning, parking, buffers and access. Power capacity and water demand in gallons are not in it, and power and water are among the questions the regional review and the advocacy groups raised; the report itself notes that employee counts have not been provided.

As we read the water section, Savannah’s role is a bridge: the city says it would only briefly supply the first phase until a new Effingham County treatment plant comes online in early 2030, so the project’s early water depends on that plant’s timing.

Effingham County staff report, Project Camellia site plan, for the 3 November 2026 meeting

“The proposed development meets the applicable zoning and site plan requirements of the I-1 (Industrial) district, including parking, buffering, and access standards.”

Three Implications

FOR OPENAI The staff report says the plan meets the industrial district’s site-plan rules, and an OpenAI spokesperson told the Savannah Morning News the company is committing more than $20 million to wetland mitigation.

FOR EFFINGHAM COUNTY The staff report says employee counts have not been provided and that parking compliance will be verified during development plan review.

FOR THE REGION’S WATER AND POWER The regional review flagged drainage and flood risk, water use and energy supply, and One Hundred Miles asked where the project’s backup power would come from.

The Business Engineer Lens

This story maps onto the Business Engineer framework The State of AI Data Centers.

The framework reads: “The structural bottleneck isn’t computing, it’s electrons.”

As we read it, the Project Camellia file fits that framing: several of the questions raised in the regional review concern power, water and flooding. The framework is the owner’s argument and does not discuss Project Camellia.

Related coverage: Suit targets OpenAI Georgia deal carrying $900M tax break · Midterm pause pledges cover 30 GW of 2028 data centers

What Is Not Established

The staff report does not give the project’s power capacity, water demand in gallons, employee counts or a construction schedule. The OpenAI spokesperson did not say how many of the more than 1,000 positions would be permanent.

The Savannah Morning News described the site as featuring two 35-foot-tall data center buildings, citing the meeting agenda; the staff report attached to the agenda lists six data center buildings of about 42 feet. The site plan vote is a separate step from the lawsuit over the earlier agreements.

This Week In The AI Supercycle

Anthropic’s Reality Check, The Capital Squeeze, & The New World Order

This week’s issue: for two years the AI build-out was priced as a growth story. This week it started being priced as a credit story.

Read the full issue →

Business Engineer Framework

The State of AI Data Centers

A Business Engineer analysis of gigawatt-scale AI data centers and the power constraints around them.

Read the Map of AI →

The Bottom Line

Effingham County’s commissioners vote on Tuesday on a site plan that county staff say meets the industrial district’s rules: six data center buildings on about 1,347 acres, with parking that by our arithmetic matches the county ratio for 3,216 workers. Water, flooding and power are the open questions in the regional review.

95,000+ executives read Business Engineer for the AI strategy frameworks cited by ChatGPT, Claude, and Perplexity.

A note on sourcing. This piece is based on the Effingham County Board of Commissioners agenda and staff report for the 3 November 2026 meeting, the Savannah Morning News report of 2 November, and our 28 October coverage of the Project Camellia lawsuit. The 1,347-acre total and the 3,216-worker parking calculation are our arithmetic.

Sources: Effingham County Board of Commissioners agenda, 3 Nov 2026, item 16 (2026-511 Site Plan) · Effingham County staff report, Site-26-6 Project Camellia · Savannah Morning News, 2 Nov 2026