New orders for Nvidia’s B300 GPUs now take 26 to 40 weeks to deliver, and GB300 orders about 14 to 26 weeks, Taiwanese ODMs told Commercial Times in a report published on 25 November. Most new orders placed over the next two quarters are expected to ship only after the second or third quarter of 2027.
The paper also reported that Nvidia will cut GeForce RTX 50 supply and that the RTX 60 series, targeted for mass production at the end of 2027, may slip. Our Nvidia stock page tracks the company.
Important: not investment advice
This article is for information and education only. It is not investment, financial, legal or tax advice, and it is not a recommendation or an offer to buy or sell any security, ETF, option or other financial product. FourWeekMBA is not a broker-dealer or a registered investment adviser. IPO shares, leveraged and inverse ETFs, and options carry significant risk, including the loss of your entire investment; leveraged and inverse ETFs reset daily and can lose value quickly. Prices, availability, fees and eligibility change and can differ by country and broker, so check the prospectus and your broker’s terms. Figures marked “our arithmetic” are our own calculations from the cited filings and may contain errors. Do your own research and consider speaking to a licensed financial professional before making any investment decision.
Business Pill · Embedded Dependency
An evergreen Business Engineer explainer. It teaches the general idea only and does not discuss Nvidia’s lead times.
The key insight: New Nvidia B300 orders now wait 26 to 40 weeks and GB300 orders 14 to 26 weeks, Taiwanese ODMs told Commercial Times on 25 November; most orders placed over the next two quarters ship after mid-2027, and the RTX 60 gaming cards may slip.
What the Lead Times Are
Per the report, B300 GPUs take 26 to 40 weeks and GB300 about 14 to 26 weeks. The desktop GB300 superchip used in the DGX Station workstation takes about 26 weeks.
RTX Pro GPU accelerator cards for servers and workstations now take more than 26 weeks. The longest B300 wait, 40 weeks, is about nine months, by our arithmetic.
Orders already shipping, including RTX Pro AI servers, DGX Station and RTX Spark AI PCs, are not clearly affected and remain on schedule, the ODMs said.


Why Gaming Cards Lose Out
Nvidia’s main Taiwanese ODM partners have shifted to B300, GB300 and the ramping Vera Rubin platform, the paper reported. Semiconductor industry sources expect wafers not used for consumer GPUs to go to data-centre chips.
Memory is the other squeeze. Memory makers are giving advanced capacity to server DRAM first, which limits GDDR7 output for graphics cards and keeps its prices rising, per the report. Ambarella this week guided sales down 37% as memory prices bite.
Nvidia had said GeForce demand remains strong but memory supply is tight, the paper noted. On the demand side, Dell reported a $132.3 billion AI backlog on Tuesday.
The Structural Read
As we read it, lead times this long mean buyers ordering today are effectively booking 2027 capacity, which keeps Nvidia’s order book full even after this week’s chip sell-off.
As we read it, gaming cards are now the residual: wafers and memory go to data-centre chips first, so consumer supply tightens.
Commercial Times, 25 Nov 2026 (our translation)
“All new orders have much longer lead times.”
Three Implications
FOR AI BUYERS New B300 orders wait 26 to 40 weeks, per the report.
FOR GAMERS Nvidia reportedly cuts RTX 50 supply; RTX 60 may slip past end-2027.
FOR MEMORY Server DRAM gets priority; GDDR7 output for graphics cards is limited.
What Is Not Established
The lead times come from unnamed ODM and supply-chain sources quoted by Commercial Times; Nvidia has not published them. The RTX 60 delay is described as a risk, not a decision, and no new date was given.
The Bottom Line
New B300 orders now wait 26 to 40 weeks and GB300 orders 14 to 26 weeks, Commercial Times reported, with most new orders shipping after mid-2027. Nvidia will reduce RTX 50 supply, the paper reported, and industry sources expect the freed wafers to go to data-centre chips.
Important: not investment advice
This article is for information and education only. It is not investment, financial, legal or tax advice, and it is not a recommendation or an offer to buy or sell any security, ETF, option or other financial product. FourWeekMBA is not a broker-dealer or a registered investment adviser. IPO shares, leveraged and inverse ETFs, and options carry significant risk, including the loss of your entire investment; leveraged and inverse ETFs reset daily and can lose value quickly. Prices, availability, fees and eligibility change and can differ by country and broker, so check the prospectus and your broker’s terms. Figures marked “our arithmetic” are our own calculations from the cited filings and may contain errors. Do your own research and consider speaking to a licensed financial professional before making any investment decision.
97,000+ executives read Business Engineer for the AI strategy frameworks cited by ChatGPT, Claude, and Perplexity.
A note on sourcing. The lead times, the RTX 50 supply cut and the RTX 60 timing are from Commercial Times, citing unnamed Taiwanese ODMs and supply-chain sources; the article is in Chinese and the translation is ours. Nvidia has not confirmed the figures. The nine-month conversion is our arithmetic. This is not investment advice.
Sources: Commercial Times (工商時報), ‘輝達GPU新單交期拉長’ (Lead times lengthen on new Nvidia GPU orders), 25 Nov 2026 · AIStockSavvy on X, summary of the Commercial Times report, 24 Nov 2026 23:43 UTC