SpaceX says its planned supercomputer site in Cochise County, Arizona, will have “no gas plant, no industrial water use, and a dry-cooling closed-loop water system,” in a post on X on Wednesday.
Elon Musk shared it with a name: “SpaceX Colossus 3 will greatly benefit the Arizona community,” he wrote. We track the site and its local fight on our AI data centre map.
Important: not investment advice
This article is for information and education only. It is not investment, financial, legal or tax advice, and it is not a recommendation or an offer to buy or sell any security, ETF, option or other financial product. FourWeekMBA is not a broker-dealer or a registered investment adviser. IPO shares, leveraged and inverse ETFs, and options carry significant risk, including the loss of your entire investment; leveraged and inverse ETFs reset daily and can lose value quickly. Prices, availability, fees and eligibility change and can differ by country and broker, so check the prospectus and your broker’s terms. Figures marked “our arithmetic” are our own calculations from the cited filings and may contain errors. Do your own research and consider speaking to a licensed financial professional before making any investment decision.
Business Pill · Capex and Depreciation
An evergreen Business Engineer explainer. It teaches the general idea only and does not discuss SpaceX.
The key insight: SpaceX says its $50 billion Arizona site will use no gas plant and dry cooling, and that it will pay $3.6 billion for grid upgrades, ahead of a 9 December county vote the state AG wants delayed.
What SpaceX Promised
SpaceX said it will invest more than $50 billion in the area, bringing “1,000 local permanent jobs and up to 5,500 construction jobs.”
“We will pay for our own power and pay $3.6B to upgrade the grid,” the company wrote.
It added that current residents “will not subsidize this project” and that “residential rates for SSVEC customers may decrease by up to 40%.” SSVEC is the local electric cooperative.

Why It Says This Now
Arizona Attorney General Kris Mayes has asked the county to delay its 9 December vote on the $50 billion campus, as we reported on 20 November. She wants federal and state agencies to have more time to review the effects on the electric grid and water supply, KJZZ reported.
SpaceX’s reply: “We’re asking the Commission to keep it and let residents be heard.” It said it looks forward to “addressing questions during our planned meeting on December 9.”
The campus would draw up to 6 gigawatts at full buildout, AZFamily and other local outlets have reported.

The Numbers Side by Side
The $3.6 billion grid payment is about 7% of the $50 billion SpaceX says it will invest, by our arithmetic.
The same day, the FCC approved SpaceX’s request for up to 1 million satellites built as orbital data centers, FCC Chairman Brendan Carr said, as we reported.
The Structural Read
As we read it, SpaceX is answering the AG’s grid and water concerns point by point, and asking the county not to move the vote.
Three Implications
FOR RESIDENTS SpaceX says SSVEC residential rates may decrease by up to 40%; the utility has not confirmed it in sources we read.
FOR THE VOTE SpaceX wants the 9 December meeting kept; the attorney general has asked for a delay.
What Is Not Established
The rate cut of “up to 40%” is SpaceX’s claim; we have not seen SSVEC or regulators confirm it. The county has not voted, and the AG’s delay request is still open.
“Colossus 3” is Musk’s name in his post; SpaceX’s own post does not use it.
The Bottom Line
SpaceX is answering the water and power objections in public before the 9 December vote: no gas plant, dry cooling, and $3.6 billion for the grid.
Important: not investment advice
This article is for information and education only. It is not investment, financial, legal or tax advice, and it is not a recommendation or an offer to buy or sell any security, ETF, option or other financial product. FourWeekMBA is not a broker-dealer or a registered investment adviser. IPO shares, leveraged and inverse ETFs, and options carry significant risk, including the loss of your entire investment; leveraged and inverse ETFs reset daily and can lose value quickly. Prices, availability, fees and eligibility change and can differ by country and broker, so check the prospectus and your broker’s terms. Figures marked “our arithmetic” are our own calculations from the cited filings and may contain errors. Do your own research and consider speaking to a licensed financial professional before making any investment decision.
97,000+ executives read Business Engineer for the AI strategy frameworks cited by ChatGPT, Claude, and Perplexity.
A note on sourcing. SpaceX’s pledges are quoted from its own post on X; Musk’s ‘Colossus 3’ name is from his post. The AG request and 6-gigawatt figure come from our 20 November reporting of Bloomberg, KTAR, KJZZ and AZFamily. The 7% share is our arithmetic. We have not seen the utility confirm the rate claim.
Sources: SpaceX on X, 25 Nov 2026 17:07 UTC (full text) · Elon Musk on X, 25 Nov 2026 19:07 UTC: ‘SpaceX Colossus 3 will greatly benefit the Arizona community’ · SpaceX Cochise County page (linked in its post) · FourWeekMBA, 20 Nov 2026: Arizona AG asks delay on 9 December vote · AZFamily, 17 Nov 2026: SpaceX plans $50B data center campus in Cochise County









