NuScale Power incurred an expense of $507.4 million after ENTRA1 Energy signed a non-binding agreement relating to 72 of its reactor modules, and has now paid all of it, its 10-Q for the third quarter shows. NuScale settled $247.5 million in 2025 and $259.9 million in the first nine months of 2026, according to the filing of 5 November.
The trigger was the Tennessee Valley Authority’s non-binding agreement with ENTRA1, announced on 2 September 2025, to develop plants providing TVA with up to 6 gigawatts of new nuclear generation. The expense is about 1,806 times NuScale’s third-quarter revenue of $281,000, by our arithmetic.
Business Pill · Power Purchase Agreements
A short Business Engineer explainer on power purchase agreements, the binding contract that triggers the next ENTRA1 tranche. It teaches the general idea only and does not discuss NuScale, ENTRA1 or TVA.
The key insight: As we read the 10-Q, NuScale has paid ENTRA1 $507.4 million in cash for the first and smallest tranche of a three-step contribution, on an agreement that is non-binding, while its own third-quarter revenue was $281,000. The two larger tranches, 85% of the total under the agreement’s terms, depend on binding power purchase and manufacturing agreements that have not been signed.
What the 10-Q Says
Under a Partnership Milestones Agreement signed on 27 August 2025, NuScale must make “Milestone Contributions” to ENTRA1 for each NuScale Power Module (NPM) anticipated to be placed in an ENTRA1 energy project. The filing names NuScale “the key supplier to future ENTRA1 energy projects”, while ENTRA1 “retains sole and full discretion to select, contract with, or purchase from NuScale.”
The contribution comes in three tranches. The first, 15% of the total, is due on a non-binding term sheet, memorandum of understanding, letter of intent or framework agreement. The second, 35%, is due on a binding power purchase or off-take agreement. The third, 50%, is due on an equipment manufacturing agreement with NuScale for the modules.
The 10-Q says: “In 2025, the criteria for triggering payment of Milestone Contribution 1 was achieved, as ENTRA1 entered into a non-binding agreement relating to 72 NPMs.” It adds that NuScale “does not have an accrued PMA liability as of September 30, 2026”, because the criteria for the later tranches have not been met.
NuScale Corp also signed a guaranty of its operating unit’s obligations under the agreement, which runs to 31 December 2045 and renews automatically for twenty-year periods. Separately, NuScale pays ENTRA1 an annual commitment of $34.8 million under a sales and marketing agreement amended from 1 January 2025.

A Year Apart in the Income Statement
The expense sat in general and administrative costs. G&A was $519.2 million in the third quarter of 2025 and $27.9 million in the third quarter of 2026. The 10-Q attributes the $491.3 million fall mainly to “the 2025 recognition of Milestone Contribution 1 of $495.0 million associated with the signing of a non-binding agreement between ENTRA1 and TVA”.
That $495.0 million was 95.3% of the third-quarter 2025 G&A line, by our arithmetic. The notes put the full 2025 expense at $507.4 million; the filing does not reconcile the two figures in the passages we read.
Revenue was $281,000 in the third quarter of 2026, against $8.2 million a year earlier, when NuScale was still booking engineering work for the RoPower project. The net loss narrowed to $45.7 million from $532.6 million. Nine-month revenue was $921,000.

The Cash Side
The payment is cash, not an accounting entry. NuScale used $401.4 million in operating activities in the first nine months of 2026, and the 10-Q says the increase was “primarily due to the payment to ENTRA1 of $259.9 million”. That payment was 64.7% of the period’s operating cash use, by our arithmetic; the rest came to $141.5 million.
At 30 September NuScale had cash and cash equivalents of $513.4 million, short-term investments of $420.0 million and investments of $930.7 million, “with no debt”: $1.86 billion in all, by our arithmetic. The press release rounds this to $1.9 billion.
At the nine-month pace of operating cash use excluding the ENTRA1 payment, $1.86 billion equals about 9.9 years of spending, by our arithmetic. That is a pace, not a forecast. The company says it has enough cash and investments, “along with continued access to capital markets, to satisfy our cash requirements for the next 12 months and beyond.”
The cash came largely from share sales. NuScale sold 89.7 million Class A shares in the first nine months of 2026 for $1.0 billion gross at a weighted average price of $11.14, and on 11 August signed a new at-the-market sales agreement for up to $750 million.
What the Next Two Tranches Imply
If the $507.4 million first tranche is 15% of the total contribution for the 72 modules, the implied total is $3.38 billion, by our arithmetic. The second tranche would be $1.18 billion and the third $1.69 billion: $2.88 billion together, about 1.54 times NuScale’s cash and investments.
Per module, the implied total is about $47.0 million, of which the first tranche was about $7.0 million. These figures assume the same 72 modules and the same tranche shares; the 10-Q does not state the amount per module. At 77 MWe each, 72 modules are 5,544 MWe of gross capacity, by our arithmetic.
The filing ties the next step to TVA. It says the “potential next phase of the collaboration between TVA and ENTRA1” is “contingent on the execution of one or more power purchase agreements between ENTRA1 and TVA.” That is the event that triggers the 35% tranche under the agreement’s terms.
Why It Matters for AI Power
NuScale lists data centers among the uses for its 77 MWe modules, and the 10-Q says ENTRA1 and NuScale continue to develop domestic customer interest, “including interest from hyperscaler, technology, industrial and micro-grid customers”. No hyperscaler contract is named in the filing.
Other nuclear suppliers to the AI build-out are at different stages: Oklo and Centrus Energy signed fuel contracts covering five reactors (our Oklo piece), and Amazon would cover the costs of AEP’s 960MW nuclear plan (our AEP piece). A nine-stock basket of AI data-centre names that includes Oklo fell 39% (our basket piece).
In the release, chief executive John Hopkins said the Doosan Enerbility contract to fabricate the upper reactor coolant system “moves our Nuclear Regulatory Commission-approved design into actual build and sets the foundation for all modules to follow.”
The Structural Read
As we read the cash flow statement, the ENTRA1 payment was the largest single use of operating cash this year: $259.9 million of $401.4 million, or 64.7%, by our arithmetic. Excluding it, operating cash use was $141.5 million in nine months.
As we read the tranche terms, the next payment is tied to the same event that would make the TVA programme real for NuScale: a binding power purchase agreement. If that comes for the same 72 modules, the implied second tranche is $1.18 billion, by our arithmetic, against $1.86 billion of cash and investments.
NuScale Power, Form 10-Q for the quarter ended 30 September 2026
“While the Company is subject to future payments in relation to Milestone Contribution 2 and/or Milestone Contribution 3, the criteria to record such liability has not been met yet, and the Company does not have an accrued PMA liability as of September 30, 2026.”
Three Implications
FOR NUSCALE All $507.4 million of the first milestone has been paid: $247.5 million in 2025 and $259.9 million in the first nine months of 2026, per the 10-Q.
FOR THE TVA PROGRAMME The 10-Q says the potential next phase is contingent on one or more power purchase agreements between ENTRA1 and TVA; a binding PPA is the trigger for the 35% tranche.
WHAT THE RISK FACTORS SAY The quarter’s Item 1A reports no material changes from the risk factors in the 2025 annual report; the results release lists risks related to the ENTRA1 agreement among its forward-looking risks.
RELATED Our Oklo piece covers the fuel contracts for five Oklo reactors.
The Business Engineer Lens
This story maps onto the Business Engineer framework The State of AI Data Centers.
The analysis says: “The structural bottleneck isn’t computing, it’s electrons.”
As we read it, the NuScale filing shows what a supplier of those electrons pays before a single binding contract: $507.4 million to a developer for a non-binding agreement. The analysis does not discuss NuScale, ENTRA1 or TVA.
What Is Not Established
The filing does not say when, or whether, ENTRA1 and TVA will sign a binding power purchase agreement, how many modules such an agreement would cover, or what NuScale would receive per module beyond a “negotiated maximum sale price”. The per-module and total contribution figures above are our arithmetic, not disclosed amounts.
We did not contact NuScale, ENTRA1 or TVA for this piece.
The Bottom Line
NuScale has paid ENTRA1 $507.4 million because of a non-binding agreement for 72 modules, about 1,806 times its third-quarter revenue, by our arithmetic. Under the agreement’s terms, 85% of the contribution is tied to binding power purchase and manufacturing agreements that the 10-Q says have not yet been signed.
95,000+ executives read Business Engineer for the AI strategy frameworks cited by ChatGPT, Claude, and Perplexity.
A note on sourcing. Every NuScale figure is from the company’s own Form 10-Q for the quarter ended 30 September 2026, filed with the SEC on 5 November 2026, which we read in full, and from its results release filed the same day as an exhibit to an 8-K. The filing reports amounts in thousands; we round to one decimal. The ratio to revenue, the cash shares, the 9.9-year pace and the implied second and third tranche amounts are our arithmetic; the tranche amounts assume the same 72 modules and the 15/35/50 split stated in the 10-Q, and are not disclosed figures.
The quarter’s Item 1A says there have been no material changes to the risk factors in the 2025 annual report. We first saw the item in a post on X on 16 November and went to the filings. NuScale, ENTRA1 and TVA were not contacted for this piece.
Sources: NuScale Power 10-Q, Q3 2026 (filed 5 Nov 2026) · NuScale Power Q3 2026 results release (8-K Ex. 99.1, 5 Nov 2026)