Taipower Plans NT$109.6B Grid Build for TSMC’s 1nm Hub

Taiwan Power Co. (Taipower) plans to invest NT$109.6 billion in power lines and substations for the science parks around Tainan, Economic Daily News reported on Monday. That is about $3.3 billion, by our arithmetic.

TSMC is the parks’ largest investment, and the paper calls them a hub for the next-generation 1nm chip process. Taipower estimates their power demand at 8,000 megawatts (MW).

That is about a fifth of Taiwan’s record peak load, by our arithmetic. Below: what Taipower plans to build, the demand behind it, and how it fits our AI compute commitments tracker.

Business Pill · Lead Time Explained

An evergreen Business Engineer explainer. It teaches the general idea only and does not discuss Taipower or TSMC.

The key insight: Taipower plans NT$109.6 billion, about $3.3 billion by our arithmetic, of lines and substations for Tainan’s science parks, where TSMC is the largest investment, as it estimates their demand at 8,000 MW, about a fifth of Taiwan’s 2024 record peak.

What Taipower Plans to Build

The NT$109.6 billion programme has three main parts, according to the paper. Taipower plans two new substations, called Nante and Shake, to anchor supply to the parks.

It also plans a 345-kilovolt line from the Hsinta power plant to the Southern Taiwan Science Park. The third part is new substations in nearby industrial zones.

The paper did not give completion years for this programme.

Taipower estimates the Greater Tainan science parks' demand at 8,000 MW, about a fifth of Taiwan's 41,180 MW r
Taipower estimates the Greater Tainan science parks’ demand at 8,000 MW, about a fifth of Taiwan’s 41,180 MW record peak of July 2024, by our arithmetic.

The Demand Behind It

Taipower said Tainan City’s long-term demand is estimated to exceed 10,000 MW, as semiconductor processes advance and demand for AI computing surges.

Of that, the Greater Tainan science parks need an estimated 8,000 MW, more than six large gas combined-cycle units can meet, Taipower said. The parks cover about 20 square kilometres.

That works out to 400 MW per square kilometre, which Taipower called the highest power density in the world.

“Southern Taiwan Science Park plus Shalun reaching 8 million kilowatts is a major challenge for Taipower,” chairman Tseng Wen-sheng said recently, as quoted by the paper (our translation from Chinese).

How Big 8,000 MW Is

Taiwan’s peak load hit 41,180 MW on 2 July 2024, a record at the time, Focus Taiwan reported citing Taipower. The parks’ 8,000 MW would be 19.4% of that, by our arithmetic.

By Taipower’s own comparison, the parks would use more power than Greece, Singapore, New Zealand or Ireland does as a whole country.

The 1nm Link

The National Science and Technology Council has said it is planning a large new park in the Tainan system to prepare for future 1nm fabs, the paper reported. Development of the Shalun park is expected to start in 2027.

The paper said the industry expects the grid spending to support TSMC’s 1nm power supply. TSMC was not quoted. Our TSMC piece covers how much of its sales now come from AI chips.

A Second, Larger Programme

Separately, Taipower has five approved direct-supply lines from power plants to science parks, the paper reported. They need about NT$155.5 billion and are due to be finished in phases from 2026 to 2033.

Those lines serve parks across Taiwan, not only Tainan; one runs from the Hsinta plant to the Southern Taiwan and Shalun parks. Together the two programmes come to NT$265.1 billion, about $8.1 billion, by our arithmetic.

Bar chart: Taipower's NT$109.6 billion Tainan science park grid programme and NT$155.5 billion of direct-supply lines to parks, 2026-2033. Data: Economic Daily News
The Tainan programme is the smaller of two Taipower grid plans for science parks; together they come to about $8.1 billion, by our arithmetic.

Who pays for grid upgrades like these is the subject of our grid bill explainer.

The Structural Read

As we read it, power density rather than total power is the constraint Taipower is describing: 400 MW on each square kilometre.

As we read it, the 2027 start for Shalun and the 2026-2033 direct-supply lines are the dates that will show whether the grid keeps pace with the fabs.

Tseng Wen-sheng, chairman of Taipower, as quoted by Economic Daily News (FourWeekMBA translation)

“Southern Taiwan Science Park plus Shalun reaching 8 million kilowatts is a major challenge for Taipower.”

Three Implications

FOR CHIPMAKERS The paper said the industry expects the grid spending to support TSMC’s 1nm power supply.

FOR THE GRID Taipower said the parks would use more power than Greece, Singapore, New Zealand or Ireland.

FOR POLICYMAKERS The National Science and Technology Council is planning a new park for future 1nm fabs; Shalun development is expected to start in 2027, the paper reported.

What Is Not Established

The paper did not give a start or finish date for the NT$109.6 billion programme, or say how it will be funded. TSMC’s 1nm production timeline is not in the report.

This Week In The AI Supercycle

A World Without an Order, and an AI Central Bank Without a Successor

This week’s issue: the week AI memory stayed largely sold out while the people holding the shares paid: the weekly’s argument for why the AI Supercycle is not a dot-com replay, read through geopolitics, macro and technology, with the gap between building and financing the widest we’ve recorded.

Read the full issue →

Business Engineer Framework

The AI Supercycle

The Business Engineer map of who builds, finances and captures value in AI.

Read the Map of AI →

The Bottom Line

Taipower plans NT$109.6 billion, about $3.3 billion, of grid work for Tainan’s science parks, Economic Daily News reported. The parks’ estimated 8,000 MW equals about a fifth of Taiwan’s 2024 record peak, by our arithmetic. Our Taiwan AI makers piece has the sales side of the same boom.

97,000+ executives read Business Engineer for the AI strategy frameworks cited by ChatGPT, Claude, and Perplexity.

A note on sourcing. Taipower’s plans, figures and its chairman’s quote are as reported by Economic Daily News (經濟日報) on 23 Nov 2026 Taiwan time; we translated them from Chinese. The 2024 peak load is from Focus Taiwan, citing Taipower. Dollar figures use 32.87 New Taiwan dollars per US dollar (FRED, 13 Nov 2026, the latest daily rate published). The $3.3 billion, $8.1 billion, NT$265.1 billion and 19.4% figures are our arithmetic. This is not investment advice.

Sources: Economic Daily News (經濟日報), 台電將砸千億投資輸變電計畫 台積電1奈米用電穩了, 23 Nov 2026 · Focus Taiwan, Taiwan’s daily power usage hits record high, 2 Jul 2024 · FRED, Taiwan / U.S. Foreign Exchange Rate (DEXTAUS), 13 Nov 2026